On September 21, 2009, the Federal Energy Regulatory Commission (“FERC” or the “Commission”) approved an uncontested settlement with its Enforcement Litigation Staff and  Energy Transfer Partners L.P., Energy Transfer Company, ETC Marketing Ltd., and Houston Pipe Line Company LP (collectively “ETP”) for $30 million in a market manipulation case. 

On September 9, 2009, the Maryland Public Service Commission (“PSC”) rejected an application by American Electric Power Co., Inc. (“AEP”) and Potomac Edison Co. d/b/a Allegheny Energy Inc. to build 20 miles of high-voltage transmission line in Frederick County, Maryland.

On September 2, 2009, Milford Wind Corridor, LLC (“Milford”) submitted a Petition for Declaratory Order requesting the Federal Energy Regulatory Commission (“FERC” or the “Commission”) to confirm that it can retain its firm rights to use 1,000 MW of transmission on a generator lead Milford constructed itself in order to interconnect the full capacity of five planned phases of its entire wind project.