On October 23, 2026, FERC conditionally accepted the Midcontinent Independent System Operator, Inc.’s (MISO) proposal to revise its Open Access Transmission, Energy and Operating Reserve Markets Tariff (Tariff) to reform the penalties applied to Load Modifying Resources (LMRs) that fall short of their performance obligations. The revisions, which take effect
NERC Seeks FERC Approval of New Registration Categories Related to Computational Loads
On October 21, 2026, the North American Electric Reliability Corporation (NERC) submitted a Petition with FERC seeking approval of proposed Rules of Procedure revisions that add two new functional entity types to the NERC Compliance Registry—Computational Load Owner (CLO) and Computational Load Operator (CLOP). NERC proposed these Rules of Procedure revisions in response to emerging concerns over the electrical behavior of computational loads and FERC’s July 16, 2026 order directing NERC to address Bulk-Power System (BPS) reliability risks associated with the integration of computational loads.
Continue Reading NERC Seeks FERC Approval of New Registration Categories Related to Computational LoadsFERC Again Rejects Without Prejudice TransAlta’s Cost Recovery Proposal for Compliance with DOE 202(c) Order
On October 19, 2026, FERC rejected without prejudice a proposal by TransAlta Centralia Generation LLC (TransAlta) to recover the costs of complying with a United States Department of Energy (DOE) emergency order directing TransAlta to make Unit 2 of its Centralia Generation Facility (Centralia) available to operate to address an…
FERC Proposes Dropping Air Dispersion Modeling Requirement from Natural Gas NEPA Reviews
On October 15, 2026, FERC issued a draft policy statement proposing to end its requirement that natural gas and liquefied natural gas (LNG) project applicants submit air dispersion modeling for environmental reviews under the National Environmental Policy Act (NEPA). Under the draft policy statement, FERC would instead rely on equipment-specific…
FERC Accepts PJM’s Large Load and Large Load Registry Definition but Rejects Interim Resource Adequacy Service Proposal
On October 9, 2026, FERC accepted and PJM Interconnection, L.L.C.’s (PJM) proposed definition of “Large Load” and Large Load Registry under the PJM tariff, but otherwise rejected PJM’s proposed Interim Resource Adequacy Service (IRAS) and related Bring Your Own New Capacity (BYONC) frameworks. Specifically, FERC rejected PJM’s IRAS and BYONC proposals because they either appeared to be outside of FERC’s jurisdiction or had not been shown to be just and reasonable and not unduly discriminatory or preferential. Commissioner David Rosner concurred in a separate statement.
Continue Reading FERC Accepts PJM’s Large Load and Large Load Registry Definition but Rejects Interim Resource Adequacy Service ProposalFERC Initiates Rulemaking on Blanket Authorizations at LNG Plants
On October 15, 2026, FERC initiated a rulemaking to enable blanket authorizations for certain activities at liquefied natural gas (LNG) plants. In the Notice of Proposed Rulemaking (NOPR), FERC proposed to revise its regulations to allow LNG plants to modify certain LNG facilities and auxiliary facilities without needing to seek Commission approval under sections 3 or 7 of the Natural Gas Act (NGA).
Continue Reading FERC Initiates Rulemaking on Blanket Authorizations at LNG PlantsDOE Awards $1.9 Billion in SPARK Funding for Grid Modernization Projects
On September 24, 2026, the U.S. Department of Energy (“DOE”) announced the 31 transmission projects it plans to fund through the Speed to Power through Accelerated Reconductoring and Other Key Advanced Transmission Technology Upgrades (“SPARK”) program. The projects will receive $5.25 billion in total, consisting of $1.9 billion in federal…
FERC Denies Complaint Against PJM Relating to Interconnection Study Cycle 01
On September 24, 2026, FERC denied a complaint filed by Oklo, Inc. (Oklo) against PJM Interconnection, L.L.C. (PJM) alleging that PJM unlawfully administered the interconnection process to Oklo’s 750-megawatt project (Project) and unjustifiably withdrew the Project from Cycle 01. In denying the complaint, FERC found that Oklo failed to meet its burden under Federal Power Act (FPA) section 206 by failing to show that PJM violated its Open Access Transmission Tariff (Tariff).
Oklo submitted the Project’s data, signed agreement, and deposit information to PJM for Cycle 01 on April 27, 2026. PJM issued its deficiency notice on May 15, 2026, identifying six deficiencies. Oklo asserted that it timely cured the six deficiencies identified in the notice, and then on June 24, 2026, PJM identified five additional, potential deficiencies, including failure to re-submit a dynamic modeling development guidelines (DMDG) report and checklist when Oklo submitted its cure to the May 15 Deficiency Notice. On August 3, 2026, PJM then withdrew the Project from Cycle 01. On August 4, 2026, Oklo stated that PJM issued a Withdrawal Notice, explaining that the Project was deficient.
Continue Reading FERC Denies Complaint Against PJM Relating to Interconnection Study Cycle 01FERC Accepts and Suspends PJM’s Reliability Backstop Procurement Proposal, Establishes Paper Hearing Procedures, and Encourages a New Section 205 Filing
On September 29, 2026, the Federal Energy Regulatory Commission (“FERC”) accepted PJM Interconnection, L.L.C.’s (“PJM”) Reliability Backstop Procurement proposal (“RBP Proposal”), suspending the proposal for five months and establishing a paper hearing on three elements of the RBP Proposal: (1) cost allocation; (2) Transmission Owner (“TO”) exit provisions; and (3) Load-Serving Entity (“LSE”) collateral requirements. FERC also established a Federal Power Act (“FPA”) section 206 proceeding in anticipation of any changes to the RBP Proposal that may result from the paper hearing. The order, however, encourages PJM to bypass the paper hearing process by submitting a new FPA section 205 proposal that addresses the concerns described in FERC’s order.
Continue Reading FERC Accepts and Suspends PJM’s Reliability Backstop Procurement Proposal, Establishes Paper Hearing Procedures, and Encourages a New Section 205 FilingFERC Approves New Reliability Standards to Improve Physical Security Assessment at Transmission Facilities
On September 10, 2026, FERC approved a new version of a Reliability Standard proposed by the North American Electric Reliability Corporation (NERC), Reliability Standard CIP-014-4 (CIP-014-4) (Physical Security). The original version, CIP-014-1, was approved by Order No. 802 in November 2014. The stated purpose of the currently effective version of the standard is to “identify and protect Transmission stations and Transmission substations (transmission facilities), and their associated primary control centers, that if rendered inoperable or damaged as a result of physical attack could result in instability, uncontrolled separation, or Cascading within and Interconnection.” NERC explained in its petition that the new version of CIP-014 is intended to ensure an adequate and consistent approach for evaluating instability and identifying infrastructure that is critical to the operation of the Bulk Power System.
Continue Reading FERC Approves New Reliability Standards to Improve Physical Security Assessment at Transmission Facilities