On February 21, 2023, FERC accepted PJM Interconnection, L.L.C.’s (“PJM”) proposed tariff revisions governing the Locational Deliverability Area Reliability Requirement (“LDA Reliability Requirement”) calculation, effective December 24, 2022, and applicable to the 2024/2025 Base Residual Auction (“BRA”), which was in progress at the time that PJM submitted its filing. Specifically, FERC accepted tariff changes that would allow PJM, during the BRA process, to exclude Planned Generation Capacity Resources from the LDA Reliability Requirement calculation if the addition of such resources materially increases the reliability requirement and such resources do not participate in the capacity auction. The February 21 Order also dismissed as moot a complaint filed by PJM challenging the justness and reasonableness of the existing LDA Reliability Requirement. Finally, the February 21 Order stated that FERC would soon convene a forum to examine the functioning of the PJM capacity market. Commissioner Danly issued a separate dissenting statement.

Continue Reading FERC Accepts PJM Capacity Market Revisions to Locational Deliverability Area Reliability Requirement, Sparks Strong Dissent from Commissioner Danly

On February 16, 2023, FERC addressed arguments raised on rehearing of its August 31, 2022, order accepting Midcontinent Independent System Operator, Inc.’s (“MISO”) proposal to establish a seasonal resource adequacy construct with availability-based resource accreditation (“August 2022 Order”). In doing so, FERC continued to find that MISO’s proposed transition from an annual planning resource auction to an independent auction to meet seasonal requirements is just and reasonable.

Continue Reading On Rehearing, FERC Accepts MISO’s Seasonal Resource Adequacy Construct

On March 1, 2023, FERC partially approved ISO New England’s (“ISO-NE”) proposed tariff revisions in compliance with Order No. 2222, which removed barriers to the participation of distributed energy resource (“DER”) aggregations in the capacity, energy, and ancillary services markets operated by Regional Transmission Organizations and Independent System Operators (“RTO/ISO”). In the order, FERC directed ISO-NE to revise its proposal regarding small utility opt-in requirements, capacity market participation, information and data requirements, and metering and telemetry system requirements. Commissioner Christie dissented from the order arguing that ISO-NE’s proposed metering and telemetry requirements for DER aggregations are reasonable and should be encouraging RTO/ISOs to adopt rigorous measurement and verification (“M&V”) measures, not undercutting them. Commissioner Danly concurred with a separate statement, expressing how this decision underscores his original concerns with Order No. 2222, namely that FERC is interfering in managing RTO activities that, in his view, should be under state jurisdiction. Commissioner Clements also concurred with a separate statement urging ISO-NE to make its proposal open to all DERs, such as behind-the-meter DERs.

Continue Reading FERC Partially Accepts ISO-NE Order No. 2222 Compliance Filing, but Expresses Concern that Proposal Could Create Undue Barrier to DERs

On February 14, 2023, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) upheld FERC’s March 2021 order granting Broadview Solar, LLC’s (“Broadview”) hybrid solar and battery project qualifying facility (“QF”) status (see March 25, 2021 edition of the WER) based on FERC’s interpretation of the Public Utility Regulatory Policies Act of 1978 (“PURPA”). Specifically, the D.C. Circuit determined, among other things, that FERC’s interpretation that a QF owner can use the MW net output at the point of interconnection in determining whether a facility meets the 80 MW statutory maximum for small power production facility QF status under PURPA was reasonable.

Continue Reading D.C. Circuit Upholds FERC Interpretation of PURPA Size Limitation Based on “Send out” to Point of Interconnection

On February 10, 2023, FERC approved the Western Resource Adequacy Program (“WRAP”) proposed by the Western Power Pool (“WPP”). The voluntary program commits participants to demonstrate prior to a given Winter or Summer season that they have sufficient capacity to meet a required planning reserve margin and have reserved 75% of the transmission to deliver that capacity to load. The WRAP also allows those who are short on capacity to call on the excess capacity of other participants during critical periods. The Southwest Power Pool, Inc. will run the operations of the program, which became effective January 1, 2023, under the oversight of WPP.

Continue Reading FERC Approves Regional Resource Adequacy Program in the Western Interconnection

On February 16, 2023, FERC approved two new extreme cold weather Reliability Standards—EOP-011-3 (Emergency Operations) and EOP-012-1 (Extreme Cold Weather Preparedness and Operations)—filed by the North American Electric Reliability Corporation (“NERC”) and aimed at implementing the recommendations resulting from a joint inquiry into the circumstances surrounding Winter Storm Uri. However, FERC also directed modifications to EOP-012-1 to address what FERC characterized as concerns over the Standard’s applicability, ambiguity, lack of objective measures and deadlines, and prolonged, indefinite compliance periods. The new Reliability Standards constitute the first phase of NERC’s effort to implement the recommendations resulting from the joint inquiry into the 2021 winter storm. NERC stated that it will address the remaining recommendations in the second phase of the project.

Continue Reading FERC Approves Extreme Cold Weather Reliability Standards in Response to Winter Storm Uri

On January 31, 2023, the Federal Energy Regulatory Commission (“Commission” or “FERC”) granted Great River Energy’s (“GRE”) requested incentive rate treatment for GRE’s investment in the Iron Range Project and Big Stone Project (collectively, “Projects”). Notwithstanding FERC’s approval, Commissioner Christie’s separate concurrence highlighted persistent concerns over the Commission’s incentive rate treatment policy.

Continue Reading FERC Commissioner Christie Renews Concerns Over Transmission Rate Incentives in MISO Transmission Expansion Plan Order

On January 27, 2023, FERC approved the Midcontinent Independent System Operator, Inc. (“MISO”) Transmission Owners’ (“TOs”) proposal to terminate reactive power charges and compensation under MISO’s Open Access Transmission, Energy, and Operating Reserve Markets Tariff (“Tariff”), effective December 1, 2022.  As a result, MISO will no longer charge transmission customers for reactive power service within the standard power range, and no generators, whether affiliated with the MISO TOs or not, will receive compensation for providing reactive power service within the standard power factor range.  Nevertheless, FERC’s determination does not affect MISO generators’ ongoing obligation to provide reactive power.  If MISO directs a generator to provide reactive power outside of the standard power factor range, the generator will be compensated based on existing mechanisms already included in MISO’s Tariff.  

Continue Reading FERC Allows MISO Transmission Owners to Retroactively Terminate Reactive Power Compensation Back to December 2022

On January 23, 2023, FERC set New York Power Authority’s (“NYPA”) proposed revisions to its Formula Rate Template for hearing, including changing NYPA’s allocation methodology for administrative and general (“A&G”) costs to a multi-factor, modified Massachusetts method (“Massachusetts Method”). In doing so, FERC found that NYPA had not supported its claim that the Massachusetts Method is appropriate for its specific circumstances and organizational structure or how the change would affect rates. FERC also conditionally accepted proposed changes to NYPA’s Formula Rate Protocols implementing transmission rate incentives and cost containment mechanisms for the Smart Path Connect Project.

Continue Reading FERC Sets NYPA Formula Rate Changes for Hearing, Including Proposed Template Utilizing “Massachusetts Method” for A&G Cost Allocation.

On February 8, the U.S. Department of Energy (DOE) released draft guidance (Draft Guidance) on the Infrastructure Investment and Jobs Act (Act) (known as the Bipartisan Infrastructure Law) Section 247 incentive, one of the key hydroelectric provisions  offered by the legislative package. The Act, which President Biden signed in November 2021, provides $553.6 million in total funding to the Section 247 program for “capital improvement” projects that maintain and enhance existing hydroelectric facilities to ensure generators continue to provide clean electricity, while integrating renewable energy resources such as wind and solar, improving dam safety, and reducing environmental impacts. The Draft Guidance focuses on the Section 247 application process and how DOE will rate and select incentive recipients.  DOE will accept comments on the Draft Guidance until February 28th, which provides hydropower licensees an opportunity to help shape the final guidance, and alert DOE to any potential obstacles that could prevent licensees from successfully participating in the Section 247 program.

Continue Reading DOE Releases Awaited Draft Guidance for Bipartisan Infrastructure Law Hydropower Incentive