On June 16, 2015, the U.S. Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) denied a consolidated Petition for Review of several of Kern River Gas Transmission Company’s (“Kern River”) FERC-approved transportation rates. In doing so, the D.C. Circuit held that FERC acted reasonably in setting the rates, responded meaningfully to rate objections, and articulated a rational explanation of its decisions.
Uncategorized
FERC Adopts Revisions to Exhibit Submission Requirements for Trial-Type Evidentiary Hearings
At its June 18, 2015 monthly Commission meeting, FERC issued a final rule adopting revisions to Rule 508 of its Rules of Practice and Procedure which eliminate the requirement that participants in FERC trial-type evidentiary hearings provide paper copies of all exhibits introduced as evidence. According to FERC, the final rule facilitates a shift toward electronic hearing procedures, while still retaining the option to provide exhibits in paper form.
FERC Denies Duke Energy’s Complaint against PJM, Initiates Investigation
On June 9, 2015, the Commission denied Duke Energy Corporation’s (“Duke”) complaint against PJM Interconnection, L.L.C. (“PJM”) in which Duke alleged that PJM failed to reimburse Duke for fuel PJM directed Duke to purchase so that certain gas-fired generating units would be available to run during the January 2014 polar vortex. Although it dismissed Duke’s complaint, the Commission also initiated an investigation to examine whether certain provisions of PJM’s Open Access Transmission Tariff (“OATT”) are unjust, unreasonable, unduly discriminatory, or preferential because they: (i) do not allow market participants to submit day-ahead offers that vary by hour; and (ii) do not allow market participants to update their offers in real time, including during emergency situations.
FERC Conditionally Approves PJM’s Capacity Market Reforms; Chairman Bay Dissents
On June 9, 2015, FERC conditionally approved significant reforms to PJM Interconnection LLC’s (“PJM”) capacity market framework. In doing so, FERC stated that PJM had demonstrated that the reforms were needed in order to ensure the long-term reliability of the electric supply within the PJM region. Meanwhile, Chairman Norman Bay dissented, stating that PJM’s proposal was seriously flawed, and may “result in billions in additional costs for consumers without achieving its intended aim.”
D.C. Circuit Rejects Challenges to EPA’s Proposed Greenhouse Gas Rule
On June 9, 2015, the U.S. Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) dismissed challenges to the Environmental Protection Agency’s (“EPA”) proposed rule reducing carbon dioxide emission limits from existing power plants (“Proposed GHG Rule”). In doing so, the D.C. Circuit held that it did not have the authority to review the Proposed GHG Rule because it was still being drafted and, therefore, no final agency action subject to judicial review existed.
D.C. Circuit Denies Review of EPA’s Designations of Ozone Attainment Rule
On June 2, 2015, the U.S. Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) denied nineteen consolidated petitions for review of the Environmental Protection Agency’s (“EPA”) compliance determinations with EPA’s 2008 ground-level ozone standards, known as the National Ambient Air Quality Standards (“NAAQS”). By denying review, the D.C. Circuit affirmed EPA’s authority to make such compliance determinations under the Clean Air Act, and upheld EPA’s interpretation of the Clean Air Act and EPA’s corresponding obligations as applied to the NAAQS.
FERC Issues Civil Penalties against Powhatan and Energy Trader for Market Manipulation
On May 29, 2015, FERC assessed civil penalties against Powhatan Energy Fund LLC (“Powhatan”), Dr. Houlian Chen, and two funds owned by Dr. Chen, HEEP Fund, LLC (“HEEP”) and CU Fund, Inc. (“CU Fund”) (collectively, “Parties”) for market manipulation in PJM Interconnection L.L.C.’s (“PJM”) energy markets. In doing so, FERC held that the Parties engaged in fraudulent Up-To Congestion (“UTC”) transactions to garner excessive amounts of transmission credits. The civil penalties include a $16.8 million penalty against Powhatan, a $10.8 million penalty against CU Fund, a $1.92 million penalty against HEEP, and a $1 million penalty against Dr. Chen. FERC also ordered disgorgements against Powhatan for $3,465,108, CU Fund for $1,080,576, and HEEP for $173,100.
NERC Issues 2015 State of Reliability Report
On May 28, 2015, the North American Electric Reliability Corporation (“NERC”) issued its annual State of Reliability Report (the “Report”), and made several key findings regarding the reliability of the Bulk-Power System (“BPS”). According to NERC, the goal of the Report was to “quantify risk and performance, highlight areas for improvement, and reinforce and measure success in controlling risks to reliability.” NERC based much of its analysis on data collected from January 2014 through December 2014.
FERC Approves $16 Million Civil Penalty in Settlement with WECC over Southwest Blackout
On May 26, 2015, FERC approved a stipulation and consent agreement (“Settlement”) between FERC’s Office of Enforcement (“Enforcement”) and the North American Electric Reliability Corporation (“NERC”), and the Western Electricity Coordinating Council (“WECC”) and Peak Reliability—WECC’s NERC-certified Reliability Coordinator. Among other items, the Settlement provides for a $16 million civil penalty against WECC, and resolves FERC and NERC’s investigation of WECC for Reliability Standard violations that contributed to the September 8, 2011 Southwest Blackout.
NRC to Consider Variable Annual Fee for Small Nuclear Reactors
On May 15, 2015, the Nuclear Regulatory Commission (“NRC”) approved a staff proposal to develop “variable” fees for small modular reactors (“SMRs”) through a subsequent rulemaking process. The annual fees could then be modified for individual SMRs based on megawatt capacity. Currently, annual fees are allocated equally among all operating nuclear reactors. The annual fees are used to fund 90 percent of the NRC’s budget, as required by law.