On February 2, 2015, the Commission directed Maxim Power Corporation, Maxim Power (USA), Inc., Maxim Power (USA) Holding Company Inc., Pawtucket Power Holding Co., LLC, Pittsfield Generating Company, LP (collectively “Maxim”), and Kyle Mitton, a Maxim executive (together “Respondents”) to show cause why they should not be found to have violated the Federal Power Act and the Commission’s regulations “through a scheme to obtain payments for reliability dispatches based on the price of expensive fuel oil when Maxim in fact burned much less costly natural gas.” The Commission further directed the Respondents to show cause why they should not be assessed civil penalties of: (i) $50,000 (against Mr. Mitton); and (ii) $5,000,000 (against Maxim).
Uncategorized
FERC Waives MISO Energy Offer Price Cap for Winter Season
On February 9, 2015, FERC approved the Midcontinent Independent System Operator, Inc.’s (“MISO”) request for a temporary waiver of its $1,000/MWh energy offer price cap. FERC’s approval will now allow generators with actual, verifiable costs above the $1,000/MWh energy offer price cap to receive make-whole payments by increasing the “No Load” component of their offer after consultation with MISO’s Independent Market Monitor (“IMM”). The waiver of the energy offer price cap runs from December 20, 2014 to April 30, 2015.
FERC Eliminates e-Tag Requirement for EQRs
On February 6, 2015, FERC ruled, in its Order on Rehearing regarding certain reporting requirements of Order No. 768, that Electronic Quarterly Reports (“EQR”) filers will no longer need to submit an electronic tag (“e-Tag”) ID for each transaction reported in their EQRs if an e-Tag was used to schedule the transaction.
FERC Denies Complaint against ISO-NE to Eliminate the “Peak Energy Rent” Adjustment in its Forward Capacity Market
On January 30, 2015, the Commission denied a complaint filed by the New England Power Generators Association, Inc. (“NEPGA”) in which NEPGA sought either modification or elimination of the Peak Energy Rent (“PER”) Adjustment mechanism in ISO New England Inc.’s (“ISO-NE”) Forward Capacity Market (“FCM”).
DOE Inspector General Releases Findings on FERC’s Handling of Nonpublic Information
On February 4, 2015, the Department of Energy’s (“DOE”) Office of the Inspector General released a report on the Federal Energy Regulatory Commission’s (“Commission”) treatment of nonpublic information within the Commission (“Inspection Report”). The “Inspection Report: Review of Controls for Protecting Nonpublic Information at the Federal Energy Regulatory Commission” concluded that the “Commission’s controls, processes and procedures for protecting nonpublic information were severely lacking.”
FERC Submits Fiscal Year 2016 Budget Request
On February 2, 2015, FERC submitted its Fiscal Year (“FY”) 2016 Budget Request for $319,800,000. This amount is approximately five percent above the FY 2015 Budget Request. In requesting its budget, FERC sets out its three primary goals: (1) supporting just and reasonable rates, terms, and conditions (“Goal 1”); (2) promoting safe, reliable, secure and efficient infrastructure (“Goal 2”); and (3) mission support through organizational excellence (“Goal 3”).
FERC Approves SPP/MISO Protocols Aimed at Managing Seams Congestion
On January 22, 2015, the Commission conditionally approved Southwest Power Pool’s (“SPP”) proposed “Market-to-Market” coordination protocols with the Midcontinent Independent System Operator (“MISO”), and, among other things, made determinations on several key issues relating to the protocols that were examined during a technical conference held in September.
FERC Seeks Comments on Price Formation Workshop Topics
On January 16, 2015, FERC issued a notice inviting parties to submit post-technical workshop comments regarding price formation in both the energy and ancillary services markets that are operated by Regional Transmission Organizations (“RTOs”) and Independent System Operators (“ISOs”). Previously, FERC Staff conducted a series of technical workshops on September 8, October 28, and December 9, 2014, exploring these same price formation issues (see Sept. 15, 2014 edition of the WER). FERC’s January notice invites parties to respond to specific questions that will further explore the topics that had been covered in the 2014 workshop series.
DOE Announces $59 Million Investment in Solar Power
On January 29, 2015, the Department of Energy (“DOE”) announced more than $59 million in funding for solar energy technologies and projects. DOE further clarified that the funding will be divided into two project categories – $45 million for solar manufacturing technologies that can be brought to market, and $14 million for community-based, multi-year deployment plans. DOE also noted that the funding will help support the White House’s effort to double renewable energy generation by year 2020.
FERC Proposes Policy Clarifying Hold Harmless Commitments
On January 22, 2015, FERC issued a proposed policy statement to clarify FERC’s policy regarding the use of hold harmless commitments in Federal Power Act section 203 applications. Under the proposed policy statement, applicants will still be required to demonstrate that the proposed transaction does not have an adverse effect on rates, but FERC will define with greater specificity what costs will be considered transaction-related costs and how hold harmless commitments will apply.