On January 17, 2019, FERC denied North Carolina Electric Membership Corporation’s (“NCEMC”) Formal Challenge and Complaint against Duke Energy Progress, LLC’s (“DEP”) transmission formula rate and Joint Open Access Transmission Tariff (“Joint OATT”) for failing to reflect in its wholesale transmission rates reductions related to federal, and North Carolina state, corporate income tax changes. For various reasons discussed below, FERC denied NCEMC’s Complaint because it found that DEP had correctly applied its historical test year formula rate methodology.
D.C. Circuit Denies SDG&E Petition for Review of FERC Orders Denying Retroactive Abandonment Incentive
On January 15, 2019, the U.S. Court of Appeals for the D.C. Circuit (“D.C. Circuit”) in San Diego Gas & Electric Co. v. FERC, No. 16-1433, denied San Diego Gas & Electric’s (“SDG&E”) petition for review of FERC orders declining retroactive application of its cancelled or abandoned electric transmission facilities incentive (“Abandonment Incentive”). The D.C. Circuit’s decision denies SDG&E the eligibility to recover, in the case of abandonment, approximately $15 million in development costs associated with its South Orange County Reliability Enhancement Project (“SOCRE Project”). The decision also prompted a dissent from Senior Circuit Judge A. Raymond Randolph, who argued that the underlying FERC orders were contrary to the plain language of the regulation at issue, as well as the Commission’s own precedent.
D.C. Circuit Denies Review of FERC Orders in Hydro Project Relicensing
On January 18, 2019, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) denied a petition by the State of North Carolina to review two FERC orders involving the relicensing of the Yadkin River Hydroelectric Project (“Yadkin Project”) in North Carolina. The D.C. Circuit found substantial evidence supporting FERC’s decision to deny North Carolina’s allegations of misrepresentation by Alcoa Power Generating, Inc. (“Alcoa”), the license applicant, and to grant a new operating license to Alcoa for the Yadkin Project. The court also rejected North Carolina’s proposal to invoke the federal recapture provision of the Federal Power Act (“FPA”) to the state at Alcoa’s net investment plus severance damages.
FERC Approves PJM Tariff Revisions Regarding Transmission Constraint Penalty Factors
On January 8, 2019, FERC approved revisions to the PJM Interconnection, L.L.C. (“PJM”) Tariff and Operating Agreement regarding the use of transmission constraint penalty factors in its market operations. PJM’s filing responds to new market transparency requirements set out in Order No. 844, the result of FERC’s rulemaking addressing uplift cost allocation and transparency in Regional Transmission Organizations (“RTOs”) and Independent System Operators (“ISOs”). In accepting PJM’s proposed revisions, FERC found the revisions would provide transparency regarding PJM’s transmission constraint penalty factor procedures and also produce more transparent and appropriate pricing and investment signals that correspond to an underlying transmission constraint.
District Court Rules FERC Enforcement Claim Not Barred by Statute of Limitations
On January 4, 2019, the U.S. District Court for the District of Maine (“Maine District Court”) issued an order on two motions for summary judgment concluding that FERC’s assessment of a civil penalty against Competitive Energy Services, LLC (“CES”) and its managing member, Richard Silkman (collectively, “Respondents”) was not time-barred by the statute of limitations under 28 U.S.C. § 2462. In doing so, the Maine District Court denied the Respondents’ motion for summary judgment.
Commissioner McNamee Unlikely to Recuse Himself from FERC Grid Resiliency Proceeding Unless it “Closely Resembles” DOE Resiliency NOPR
On January 7, 2019, FERC Commissioner Bernard McNamee signaled in a letter to members of the United States Senate (“January 7 Letter”) that he would not recuse himself from FERC’s pending grid resiliency proceeding in Docket No. AD18-7 unless the FERC proceeding began to “closely resemble” a Notice of Proposed Rulemaking (“NOPR”) issued in September 2018 by the Department of Energy (“DOE”). Commissioner McNamee helped draft the DOE NOPR, which also addressed grid resiliency issues and was rejected by FERC in Docket No. RM18-1 in January 2018 (see January 17, 2018 edition of the WER), when he was an attorney at the DOE. The January 7 Letter responded to a December 12, 2018 request from a group of Senators, led by Catherine Cortez Masto (D-NV), that Commissioner McNamee provide an update on the guidance he received from FERC ethics officials regarding his recusal from specific proceedings. According to that guidance, notwithstanding the similarities between Docket No. AD18-7 and the now-terminated Docket No. RM18-1 on the DOE NOPR, previous statements by Commissioner McNamee did not meet the legal standard for recusal, although the guidance urged “continued oversight to ensure that Docket No. AD18-7 does not develop in such a way as to replicate or closely resemble Docket No. RM18-1.”
EPA Proposes to Find the Mercury and Air Toxics Standards Not Cost Justified
On December 28, 2018, the U.S. Environmental Protection Agency (“EPA”) released a pre-publication version of a proposal revisiting the cost analysis underlying the Mercury and Air Toxics Standards (“MATS Rule” or “MATS”) for coal- and oil-fired electric generating units (“EGUs”) and conducting the residual risk and technology review required by the Clean Air Act (“Proposal”). The Proposal would reverse a previous finding, issued by EPA under the Obama Administration, that regulation of hazardous air pollutant (“HAP”) emissions from EGUs under the MATS Rule was “appropriate and necessary” but would nonetheless leave the rule in effect. The Proposal also concludes that more stringent HAP emission limits are not warranted by the required risk and technology reviews.
Advocates Request Recusal of Newly-Confirmed Commissioner McNamee from Grid Resiliency Proceedings
On December 6 and December 18, 2018, various environmental groups filed a motion and comments with FERC requesting that Commissioner Bernard McNamee recuse himself from FERC’s two ongoing grid resiliency proceedings. The groups argued that because Commissioner McNamee represented the Department of Energy (“DOE”) when the agency proposed compensating “fuel-secure” units for their contribution to the resilience of the electrical grid, recusal is appropriate because he is already a party to the proceedings, and in any event, may have already “prejudged” central matters of law and fact relevant to those dockets.
FERC Addresses ADIT-Related Formula Rate Calculations for Certain Utilities
On December 20, 2018, FERC issued a series of nine orders addressing how certain public utilities calculate accumulated deferred income tax (“ADIT”) balances in their transmission formula rates. The orders were the result of separate proceedings under Section 206 of the Federal Power Act (“FPA”), which FERC initiated after concluding in a June 21, 2018 order (“June Order”) that the use of its former “two-step” ADIT averaging methodology may be unjust and unreasonable.
FERC Eliminates Form 80 for Hydroelectric Projects
On December 18, 2018, FERC eliminated the requirement for hydroelectric project licensees to file Form 80, which solicited information on the use and development of recreation facilities at FERC-licensed hydropower projects. FERC also revised Sections 8.1 and 8.2 of its regulations to (1) modernize licensee public notice practice, (2) clarify recreational signage requirements, and (3) provide flexibility to assist licensees’ compliance with these requirements. The Final Rule will go into effect 90 days after it is published in the Federal Register.