On August 9, 2019, the Federal Energy Regulatory Commission (“FERC”) ruled that hundreds of millions of dollars of ongoing and future investments by Chelan County Public Utility District (“Chelan PUD”) in the Rock Island Hydroelectric Project qualified as early-action investments under the new section 36(c) of the Federal Power Act (“FPA”).  Accordingly, FERC will consider these significant investments when the Rock Island Project undergoes relicensing of its FERC license prior to the 2028 expiration of the license.