On April 30, 2021, FERC accepted the California Independent System Operator Corporation’s (“CAISO”) submission of two proposals to revise its Tariff to amend provisions for its Energy Imbalance Market (“EIM”). In its first set of EIM enhancements, CAISO proposed to require EIM participants to settle deviations in their base schedules through CAISO’s market at a common location and price, eliminating EIM participants’ option to settle deviations in their base schedules bilaterally. In its second set of EIM enhancements, CAISO proposed to allow EIM participants the option not to have CAISO settle unaccounted for energy within an EIM participant’s balancing authority area (“BAA”), which results in a charge or credit to the affected EIM entity and can cause potential cost shifting in an EIM entity’s unaccounted for energy settlement. FERC accepted CAISO’s first proposal to be effective May 1, 2021, and the second set to be effective October 1, 2021.
FERC Revises Policy on Authorizing Pipelines to Commence Construction Pending Requests for Rehearing of Certificate Orders
On May 4, 2021, FERC issued Order No. 871-B, clarifying that the rule established in Order No. 871, which precludes FERC from authorizing natural gas pipeline companies to proceed with construction of approved pipeline projects, only applies until the earlier of either (a) the date that a qualifying rehearing request is no longer pending before FERC or (b) 90 days following the date that a qualifying request for rehearing may be deemed denied by operation of law. FERC also limited the application of this rule to requests for rehearing that raise issues reflecting opposition to project construction, operation, or need. Finally, FERC announced a general policy to stay Natural Gas Act (“NGA”) section 7 certificate orders during the rehearing period and pending resolution of any timely requests for rehearing. Commissioner James Danly dissented, arguing that the need for Order No. 871 is obviated by further developments on appeal of FERC’s practice of indefinite tolling orders before the U.S. Court of Appeals for the D.C. Circuit (“D.C. Circuit”) and that presumptively staying pipeline project construction is contrary to the NGA and is “bad policy.” Commissioner Mark Christie concurred with Order No. 871-B.
FERC Rejects PJM ELCC Proposal Based on Transition Mechanism; Establishes Paper Hearing Procedures
On April 30, 2021, FERC rejected PJM Interconnection, L.L.C.’s (“PJM”) proposed revisions to both its Tariff and its Reliability Assurance Agreement (“RAA”) to implement an Effective Load Carrying Capability (“ELCC”) construct for determining capacity values for Variable Resources, Limited Duration Resources, and Combination Resources. PJM also proposed to update its capacity value analysis annually based on variations in resource deployment and load. To account for changes in capacity values from one year to the next, PJM had proposed a transition mechanism that would establish ELCC floor values for resources on a rolling annual basis for 13 years after they enter the PJM capacity market. FERC rejected PJM’s ELCC proposal, finding the proposed transition mechanism to be unjust and unreasonable. However, FERC found that aside from the transition mechanism, other portions of the ELCC framework appear to be just and reasonable for determining accredited capacity values. FERC lifted its previously-established abeyance on the paper hearing procedures addressing PJM’s capacity valuation method, and established a briefing schedule. FERC acknowledged that PJM is under no obligation to implement its ELCC proposal prior to the next Base Residual Auction (for Delivery Year 2022/2023), but emphasized that it “specified an expedient paper hearing schedule to investigate the justness and reasonableness of PJM’s existing capacity valuation methods as soon as possible.” Commissioner Christie issued a separate concurring statement.
FERC Issues Policy Statement on Carbon Pricing in Organized Wholesale Electric Markets
On April 15, 2021, FERC issued a long-awaited policy statement providing guidance on incorporating state-determined carbon pricing into organized markets operated by Regional Transmission Organizations (“RTOs”) and Independent System Operators (“ISOs”). The non-binding policy statement explains how FERC will review and consider rate filings submitted under section 205 of the Federal Power Act (“FPA”) to establish market rules for incorporating state-determined carbon pricing into RTOs and ISOs.
FERC Proposes Reforms to RTO Participation Incentive in Supplemental NOPR
On April 15, 2021, FERC issued a Notice of Proposed Rulemaking (“NOPR”) to supplement the March 2020 NOPR regarding its electric transmission incentive policy under Federal Power Act (“FPA”) section 219 (see March 23, 2020 edition of the WER). While FERC’s March 2020 NOPR proposed to provide all utilities that turn over their wholesale transmission facilities to a Regional Transmission Organization (“RTO”) a fixed 100 basis-point increase in return on equity (“ROE”) (“RTO Participation Incentive”), the Supplemental NOPR proposes instead to codify its current practice of granting a 50 basis-point RTO Participation Incentive for utilities that join an RTO. In addition, FERC proposes that a utility will only be eligible for the incentive for the first three years after transferring operational control of its facilities to an RTO. The Supplemental NOPR also seeks comment on whether the RTO participation adder should be available solely to utilities that join an RTO voluntarily, and if so, how FERC should determine that the decision to join was voluntary. Commissioner Mark Christie issued a separate concurring statement, and Commissioners Neil Chatterjee and James Danly each issued separate dissenting statements.
FERC Confirms NYTOs Federal Right of First Refusal to Build and Recover Cost of Upgrades to Existing Transmission Facilities
On April 15, 2021, FERC issued a declaratory order confirming that under FERC Order No. 1000, incumbent New York Transmission Owners (“NYTOs”) have a federal right of first refusal (“ROFR”) for upgrades to their existing transmission facilities, including upgrades that are part of another Developer’s transmission project selected in the regional transmission plan for cost allocation. Specifically, FERC declared that the foundational agreements and Section 31.6.4 of the New York Independent System Operator, Inc. (“NYISO”) Open Access Transmission Tariff (“OATT”) established a ROFR of NYTOs to build, own and recover the cost of transmission upgrades to their existing facilities. In the same order, FERC denied requested clarification from the NYISO that such ROFR-exercising NYTOs could be considered “Developers” under the transmission planning process. FERC also provided additional clarity on the distinction between ROFR-eligible “upgrades” and new transmission facilities, indicating that different physical configurations resulting in power flow changes, increasing voltage/transfer capability, and performing different transmission functions, likely fall outside of traditional “upgrades.”
FERC Accepts NYISO Co-Located Storage Resource Participation Model
On March 30, 2021, FERC accepted the New York Independent System Operator’s (“NYISO”) proposed Co-located Storage Resource (“CSR”) Participation Model to enable energy storage resources (“ESRs”) paired with wind or solar resources to share a common point of injection and participate in the NYISO-administered markets. FERC’s order accepted revisions to NYISO’s Energy and Ancillary Services (“E&AS”) market rules, its metering rules, its Interconnection Process, its Installed Capacity Market participation rules, and its market power mitigation measures to accommodate the interconnection and participation of an ESR that is co-located with a wind or solar resource. Chairman Glick issued a concurring statement addressing NYISO’s application of existing buyer-side market power rules to co-located ESR and intermittent resources, urging NYISO “to move expeditiously to replace those rules with a model that moves beyond the minimum offer price rule as a means for mediating the interaction between state policies and wholesale markets.”
Mountain Valley Pipeline Construction to Resume over Opposition from Chairman Glick and Commissioner Clements
On March 24, 2021, FERC modified a December 17, 2020 order (“December Order”) while reaching the same overall result, allowing construction to recommence for a portion of the Mountain Valley Pipeline, LLC (“Mountain Valley”) project located near Jefferson National Forest in Virginia. FERC determined that the Environmental Conditions in Mountain Valley’s certificate order did not preclude FERC from permitting Mountain Valley to resume construction on portions of its pipeline, even though certain federal authorizations that were vacated on appeal are still pending, and also reaffirmed that completing the construction would be preferable to temporary mitigation efforts. Chairman Richard Glick and Commissioner Allison Clements dissented, arguing that FERC cannot authorize Mountain Valley to resume construction while federal authorizations remain outstanding.
Second Circuit Sides with FERC – States May Not Agree to Revise the Certification Request Date to Avoid Waiver of its Certification Authority Under Section 401 of the Clean Water Act
On March 23, 2021, the United States Court of Appeals for the Second Circuit (the “Second Circuit” or the “Court”) agreed with FERC’s determination that the New York State Department of Environmental Conservation (“DEC”) had waived its certification authority under the Clean Water Act (“CWA”) by failing to act within the one-year statutory deadline. Notably, the Second Circuit held that a state agency cannot revise a certification request date by written agreement with the applicant, thereby altering the one-year statutory deadline for state action. Denying the petitions for rehearing by DEC and the Sierra Club, the Court applied the same reasoning it applied in New York State Dep’t of Env’t Conservation v. FERC (“New York I”), 884 F.3d 450, 455-56 (2d Cir. 2018) (see March 20, 2018 edition of the WER) where the Second Circuit determined that DEC could not unilaterally alter the application date based on when it considered an application complete “because that approach would allow a state agency not only to dictate when the review process can begin but also to delay it indefinitely.” There, to avoid such a subjective standard, the Second Circuit established a bright line rule that the beginning of the review is determined by the date “of receipt of such request.”
FERC to Increase Focus on Environmental Justice
Addressing environmental justice (EJ) concerns highlighted during the campaign is an important priority for the Biden Administration. Within a week of taking the oath of office, President Biden issued a sweeping executive order with a number of EJ initiatives, including creation of a White House Environmental Justice Interagency Council consisting of the heads of each Cabinet-level and independent federal agency. The order also directed federal agencies to “make achieving environmental justice part of their missions” through development of programs and policies aimed at addressing disproportionately high adverse environmental impacts on disadvantaged communities.