On October 15, 2026, FERC issued a draft policy statement proposing to end its requirement that natural gas and liquefied natural gas (LNG) project applicants submit air dispersion modeling for environmental reviews under the National Environmental Policy Act (NEPA). Under the draft policy statement, FERC would instead rely on equipment-specific…

On October 15, 2026, FERC initiated a rulemaking to enable blanket authorizations for certain activities at liquefied natural gas (LNG) plants. In the Notice of Proposed Rulemaking (NOPR), FERC proposed to revise its regulations to allow LNG plants to modify certain LNG facilities and auxiliary facilities without needing to seek Commission approval under sections 3 or 7 of the Natural Gas Act (NGA).

On August 28, 2026, the United States Court of Appeals for the District of Columbia Circuit (D.C. Circuit) denied petitions for review of FERC’s certification of East Tennessee Natural Gas, LLC’s (East Tennessee) System Alignment Program (Project). The D.C. Circuit held that FERC did not violate customers’ due process rights…

On July 2, 2026, the Federal Energy Regulatory Commission (FERC or Commission) denied a waiver request filed by Chestnut Run Energy LLC (Chestnut Run) seeking a one-time limited waiver of certain requirements under PJM Interconnection, L.L.C.’s (PJM) Open Access Transmission Tariff (Tariff) to allow Chestnut Run to implement an equipment change to its proposed combined cycle gas turbine electric generating facility’s (Facility) configuration.  Chestnut Run sought waiver because of availability issues with certain equipment outlined in its interconnection application.  In denying the request, FERC found Chestnut Run did not demonstrate that the requested waiver would not result in undesirable consequences and noted that the requested waiver would undermine the expeditious nature of PJM’s Reliability Resource Initiative (RRI) process.

On May 21, 2026, the Federal Energy Regulatory Commission (FERC) proposed changes to its natural gas blanket certificate regulations to expand the scope and scale of projects that interstate natural gas pipelines may construct without a case-specific authorization order, and to increase the cost limits for such projects. In a companion order issued the same day, FERC extended a previously granted temporary waiver so that projects constructed and placed in service by May 31, 2028 may continue to rely on an increased prior-notice cost limit.

On March 19, 2026, the Federal Energy Regulatory Commission (“FERC”) granted Golden Triangle Storage, LLC (“Golden Triangle”) a certificate of public convenience and necessity under section 7(c) of the Natural Gas Act for its Spindletop Expansion Project (“Spindletop” or “Project”) in Jefferson County, Texas, subject to detailed engineering and environmental conditions.  In the same order, FERC reaffirmed Golden Triangle’s authority to charge market-based rates for storage and hub services and granted associated waivers of cost-based accounting and reporting requirements.

On February 19, 2026, FERC dismissed a complaint filed by Baltimore Gas and Electric Company (BGE) against Transcontinental Gas Pipe Line Company, LLC (Transco) asserting that BGE had a contractual right to challenge its negotiated rate with Transco pursuant to section 5 of the Natural Gas Act (NGA). FERC held that BGE contractually waived its NGA section 5 rights with respect to its negotiated rate, and BGE therefore was required to pay the negotiated rate.

On January 29, 2025, FERC issued a certificate of public convenience and necessity (CPCN) to Transcontinental Gas Pipe Line Company, LLC (Transco) to construct and operate its Southeast Supply Enhancement Project (Project).

The Project expands Transco’s existing natural gas transmission system in Virginia and North Carolina and will add approximately…

On December 18, 2025, FERC maintained that gas pipelines offering service under section 311 of the Natural Gas Policy Act (NGPA) that base their section 311 rates on state-approved rates must nonetheless comply with Straight-Fixed Variable (SFV) rate design or justify a departure from SFV.  Specifically, FERC denied Matterhorn Express…

On October 28, 2025, the U.S. Court of Appeals for the Fifth Circuit (Fifth Circuit) denied several petitions for review of FERC’s authorization of Gas Transmission NW, LLC’s (GTN) GTN Xpress compressor expansion project (Project).  Specifically, the Fifth Circuit (1) denied GTN’s petition for review challenging FERC’s denial of a…