On June 18, 2025, FERC temporarily raised the cost limits for blanket certificate natural gas pipeline projects constructed and placed into service by May 31, 2027, from $41 million to $61.65 million. Citing what it called a pressing nationwide near-term demand for expanded natural gas transportation capacity and reliability concerns

On May 22, 2025, the U.S. Court of Appeals for the Fifth Circuit (“Fifth Circuit”) addressed a dispute between ANR Pipeline Company (“ANR”) and FERC. The case centered on the interpretation of ANR’s tariff and whether it required shippers to deliver and take gas simultaneously, even for short-notice shipments. The Fifth Circuit denied ANR Pipeline Company’s petition for review, affirming FERC’s decision that ANR’s tariff did not require simultaneous delivery for short-notice shipments. The court found the tariff ambiguous and emphasized ANR’s longstanding practice of not requiring simultaneous delivery, which supported FERC’s position.

On May 23, 2025, FERC upheld on rehearing its prior orders authorizing Venture Global CP2 LNG, LLC to build a new liquified natural gas (“LNG”) export terminal (“CP2 LNG Terminal”) and granting Venture Global CP Express, LLC (together, with Venture Global CP2 LNG, LLC, “Venture Global”) a certificate of public convenience and necessity (“CPCN”) to construct and operate a new natural gas pipeline (“CP Express Pipeline,” together, with the CP2 LNG Terminal, the “Projects”) to connect the CP2 LNG Terminal to the existing natural gas pipeline grid (“May 23 Rehearing Order”). In its May 23 Rehearing Order, FERC continued to find that the Projects are environmentally acceptable actions and not inconsistent with the public interest.

On May 9, 2025, fifteen democratic states (“Plaintiff States”) sued the Trump Administration in Washington District Court, claiming that President Trump’s executive order “Declaring a National Energy Emergency” (“Executive Order”) is unlawful. The Plaintiff States argue that the Executive Order commands federal agencies to disregard the law and applicable regulations to fast-track activities that will damage waters, wetlands, endangered species, and the people and wildlife that rely on these resources.

On April 25, 2025, FERC approved two uncontested stipulation and agreements that propose to settle the Natural Gas Act (“NGA”) section 4 general rate cases filed on May 30, 2024, by two interconnected pipelines, Algonquin Gas Transmission, LLC (“Algonquin”) and Maritimes & Northeast Pipeline, L.L.C. (“Maritimes”). Both settlements established a 13.5% return on equity (“ROE”) for the calculation of rates for new incremental expansion projects following the settlements’ effective dates, and for the equity component of Allowance for Funds Used During Construction (“AFUDC”).

On April 24, 2025, FERC denied NGO Transmission, Inc.’s (“NGO Transmission”) application under 7(b) of the Natural Gas Act (“NGA”) to abandon its jurisdictional facilities and reclassify them from jurisdictional transmission facilities to non-jurisdictional local distribution facilities. FERC concluded that NGO Transmission’s facilities do not directly serve end-use customers in

On March 28, 2025, the D.C. Circuit denied a joint petition for review brought by Healthy Gulf and Sierra Club (together, “Petitioners”) challenging FERC’s grant of a certificate of public convenience and necessity (CPCN) to Driftwood Pipeline LLC (Driftwood) to construct two new natural gas pipelines (the “Project”) in southwestern Louisiana on grounds that FERC’s decision failed to comply with National Environmental Policy Act (NEPA) and the Natural Gas Act (NGA). The D.C. Circuit affirmed FERC’s analyses under NEPA and NGA but declined to address Driftwood’s claim that the Council on Environmental Quality’ (CEQ) regulations implementing NEPA, upon which Petitioners based their arguments, are not judicially enforceable because CEQ lacks authority to promulgate them.

On January 24, 2025, FERC reinstated a certificate of public convenience and necessity (“CPCN”) for Transcontinental Gas Pipe Line Company’s (“Transco”) Regional Energy Access Expansion Project (“Project”) after the D.C. Circuit vacated and remanded FERC’s initial order certificating the Project (“Certificate Order”).

In January 2023, FERC granted Transco a CPCN

On January 24, 2025, FERC withdrew its 2022 draft Greenhouse Gas (“GHG”) Policy Statement and terminated the associated proceeding. FERC determined that, after reviewing the entire record, issues concerning GHG emissions are better analyzed on a case-by-case basis when raised by parties in proceedings. Commissioners Phillips, Rosner, and Chang issued a joint concurrence noting that, although FERC is withdrawing its draft GHG Policy Statement, FERC still considers GHG emissions under its National Environmental Policy Act (“NEPA”) analysis and balances project benefits with potential adverse consequences under the Natural Gas Act (“NGA”).

On December 20, 2024, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) upheld FERC’s order authorizing Stingray Pipeline Company, L.L.C. (“Stingray”) to abandon a portion of its pipeline system on the condition that before doing so, Stingray either restore service or obtain a shipper agreement that the damaged pipeline segment remain out of service.