On October 10, 2025, FERC accepted Southwest Power Pool, Inc.’s (“SPP”) proposed revisions to its Open Access Transmission Tariff (“OATT”) to establish a provisional load interconnection process. SPP argued the provisional load interconnection process is driven by an increase in requests for load additions and will improve transmission planning and encourage new generation resources to come online by allowing SPP to study interconnection requests while accounting for planned generation. FERC accepted the tariff revisions subject to further compliance, finding the provisional load interconnection process will allow SPP to better understand the impacts of load requests and identify necessary network upgrades.
FERC Practice
Senate Confirms Commissioners Swett and LaCerte to Fill Remaining FERC Seats
On October 7, 2025, the U.S. Senate confirmed the nominations of Laura V. Swett and David A. LaCerte as FERC Commissioners. Once they are sworn in as Commissioners, they will fill the remaining two seats on the five-member Commission. Commissioner Swett’s term ends on June 30, 2030, and she will…
FERC Sunsets 53 Regulations in Response to April Executive Order
On October 1, 2025, the Federal Energy Regulatory Commission issued a final rule revising 53 regulations to include conditional sunset provision in response to the April 2025 Executive Order titled “Zero-Based Regulatory Budgeting to Unleash American Energy.” FERC, along with nine other agencies, was required to establish one-year…
D.C. Circuit Denies Sierra Club’s and Appalachian Voice’s Petition for Review of FERC Order Authorizing Construction and Operation of Natural Gas Pipeline
On September 30, 2025, the D.C. Circuit Court of Appeals denied a joint petition for review brought by Sierra Club and Appalachian Voices (together, Petitioners) challenging FERC’s grant of a certificate of public convenience and necessity (CPCN) to Tennessee Gas Pipeline Company (Tennessee Gas) to construct a new natural gas…
D.C. Circuit Rejects FERC’s Approval of Tennessee Gas’ Two-Tiered Fuel Rate Structure
On September 30, 2025, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) vacated and remanded FERC’s order approving a two-tiered fuel rate structure for Antero Resource Corporation’s (“Antero”) usage of Tennessee Gas Pipeline Company, L.L.C.’s (“Tennessee Gas”) Broad Run Expansion Project (“Expansion Project”). The D.C. Circuit held FERC’s approval of the rate structure was arbitrary and capricious because it required Antero to always pay for the highest fuel rates irrespective of the segment’s actual operations.
Divided Panel of the D.C. Circuit Upholds FERC’s Interpretation of PURPA Size Limitations Based on “Send Out” Capacity
On September 9, 2025, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) on remand from the U.S. Supreme Court upheld FERC’s order granting Broadview Solar, LLC’s (“Broadview”) hybrid solar and battery project qualifying facility (“QF”) status based on FERC’s interpretation of the Public Utility Regulatory Policies Act of 1978 (“PURPA”). Specifically, even without the benefit of Chevron deference (discussed below), the D.C. Circuit reaffirmed FERC’s interpretation that PURPA’s 80 MW statutory size limitation should be applied using the capacity a QF can “send out” to the grid, even if the facilities have a higher aggregate generating capacity.
FERC Requires New England Transmission Owners to Answer 2023 Annual Update Information Requests
On September 18, 2025, FERC accepted in part and denied in part the Maine Office of Public Advocate’s (“Maine OPA”) request for eight New England Transmission Owners (“Identified NETOs”) to answer information requests as part of the Information Exchange Period within their Formula Rate Protocols (“Protocols”). Three of the Identified NETOs must now answer Maine OPA’s information requests regarding procedures for evaluating the need for asset condition projects; all Identified NETOs must provide information on their respective procedures for ensuring asset condition projects are not placed in service before such projects are needed.
FERC Clears the Way for the California Independent System Operator’s Extended Day-Ahead Market
On August 29, 2025, FERC issued three orders accepting tariff revisions proposed by PacifiCorp and Portland General Electric (“PGE”) to enable both utility’s participation in the California Independent System Operator Corporation’s (“CAISO”) Extended Day-Ahead Market (“EDAM”) and accepting CAISO’s proposed tariff revisions which modify the EDAM’s allocation of congestion revenues. The three orders issued by FERC clear the way for PacifiCorp and PGE, the first two entities to file tariff revisions to participate in the EDAM, to enter the market in 2026.
FERC Reauthorizes Transco’s Northeast Pipeline Project
On August 28, 2025, FERC reauthorized Transcontinental Gas Pipe Line Company, LLC’s (Transco) Northeast Supply Enhancement Project (NESE) to deliver natural gas supply to the Northeast, including the New York City area. FERC previously issued a certificate of public convenience and necessity (CPCN) for NESE in 2019, but Transco let…
NextEra Receives FERC Waiver to Facilitate Nuclear Plant Restart in Iowa
On August 25, 2025, the Federal Energy Regulatory Commission (“FERC”) granted NextEra Duane Arnold, LLC (“NEDA”) a waiver of certain sections of the Midcontinent Independent System Operator, Inc.’s (“MISO”) tariff to use MISO’s generating facility replacement process for the recommissioning of the Duane Arnold nuclear power facility (“Project”) in Palo, Iowa. The order also extends the Project’s commercial operation date to December 31, 2029.