On June 16, FERC issued a Notice of Proposed Rulemaking (NOPR) focused on updating procedures for interconnecting large generating facilities (20MW and above) and small generating facilities (under 20MW). The NOPR proposes significant updates to FERC’s pro forma interconnection procedures, which were first established in the early 2000s. In the intervening years, however, the nation’s generation fleet has evolved, new technologies have emerged, and interconnection wait-times have steadily increased. The NOPR proposes various reforms to help address growing interconnection queue backlogs and process delays. Comments are due 100 days after the NOPR’s publication in the Federal Register. Reply comments are due 130 days after publication in the Federal Register.

Below is a summary of the primary reforms outlined in the NOPR, which fall into three broad categories: (1) implement a first-ready, first-served cluster study process; (2) increase the speed of interconnection queue processing; and (3) incorporate technological advancements into the interconnection process. FERC’s proposed reforms are discussed further in the full summary, linked below.
Continue Reading Summary of FERC Interconnection NOPR

On May 31, 2022, FERC accepted and set for hearing Southwest Power Pool, Inc.’s (“SPP”) proposal to revise its Open Access Transmission Tariff (“OATT”) to establish a formula rate template (“Formula Rate”) on behalf of People’s Electric Cooperative (“People’s Electric”) when People’s Electric transfers functional control of its transmission facilities to SPP on June 1, 2022. The Commission granted People’s Electric’s request to include a 50-basis point adder for participating as a member of SPP, a regional transmission organization (“RTO”). Commissioner Christie wrote separately in concurrence to express his continued support for limiting the RTO participation adder to three years.
Continue Reading FERC Approves ROE Adder for SPP Membership, Prompting Statement from Commissioner Christie