On May 27, 2025, FERC addressed arguments raised on rehearing of a January 30, 2025 order, which accepted the Midcontinent Independent System Operator, Inc.’s (“MISO”) proposal to modify its generator interconnection study process by implementing a queue cap and exemptions to that cap (the “Queue Cap Order”). In doing so, FERC reaffirmed that MISO’s proposed queue cap and exemptions align with Order No. 2003’s independent entity variations for regional transmission organizations and independent system operators.
Interconnection
FERC Denies Complaint Over $23 Million in Network Upgrade Costs
On March 20, 2025, FERC denied Ponderosa Power, LLC’s (“Ponderosa”) complaint alleging that NorthWestern Corporation’s (“NorthWestern”) application of its large generator interconnection procedures (“LGIP”) was unjust and unreasonable or unduly discriminatory or preferential. The dispute centered around NorthWestern’s requirement for Ponderosa to fund approximately $23 million in network upgrades to accommodate the interconnection of its 70 MW wind-powered generation facility located in Musselshell County, Montana (“Project”).
FERC Partially Accepts NorthWestern’s Order Nos. 2023 and 2023-A Compliance Filing
On November 21, 2024, FERC issued an Order partially accepting NorthWestern Energy Corporation’s (“NorthWestern”) compliance filing, effective July 10, 2024. FERC found that NorthWestern’s filing partially complies with the requirements of Order Nos. 2023 and 2023-A and directed NorthWestern to submit a further compliance filing within 60 days.
FERC Holds Workshop on Innovations & Efficiencies in Generator Interconnection Process, Seeks Comments
On September 10 and 11, 2024, FERC staff held a two-day workshop at its headquarters in Washington, DC on opportunities to further refine the generator interconnection queue process. Panelists and FERC staff discussed potential enhancements to transmission planning and processing interconnection requests over the course of six panels on discrete…
D.C. Circuit Finds That Interconnection Customers are Responsible for Network Upgrade Costs
On July 19, 2024, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) issued an Order denying Tenaska Clear Creek Wind, LLC’s (“Clear Creek”) challenges to FERC’s orders allowing the allocation of costs for network upgrades. Southwest Power Pool, Inc. (“SPP”) assigned costs of more than $100 million to Clear Creek to pay for upgrades required on SPP’s system to accommodate the interconnection of Clear Creek’s wind turbine-powered electrical generation project (the “Project”).
Troutman Pepper Summary of FERC Order No. 2023-A on Generator Interconnections
Executive Summary
On March 21, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 2023-A (Final Rule), which reaffirmed aspects of Order No. 2023 — the Commission’s landmark order updating its generator interconnection procedures. As detailed further in this summary, the Commission largely upheld Order No. 2023, including some of the more controversial aspects of the order, such as penalties and the transmission capacity “heat map,” and provided further clarity on other aspects.
FERC Approves Changes to PJM Capacity Accreditation Rules; Rejects Proposed Changes Seeking to Better Reflect Risk in Capacity Market Offers.
On January 30, 2024, FERC approved, subject to condition, PJM’s proposal to reform its Reliability Pricing Model, including resource adequacy risk modeling, capacity accreditation, testing requirements for capacity resources, and the Capacity Performance stop loss (“Modeling Enhancements Filing”). In that same order, FERC approved PJM’s proposal to replace its previously effective average Effective Load Carrying Capability (“ELCC”) capacity accreditation method with a marginal approach, effective December 12, 2023. The order directed PJM to submit a compliance filing to make certain revisions to its proposal, which PJM subsequently submitted on February 16, 2024. Additionally, on February 6, 2024, FERC rejected a companion PJM proposal to modify the rules governing its Market Seller Offer Cap and Capacity Performance construct and adopt a forward-looking Energy and Ancillary Service (“EAS”) offset for purposes of calculating the Minimum Offer Price Rule (“MOPR”) and offer cap.
FERC Rejects Solar Developer’s Request for Waiver of Security Posting Requirements After Using the Wrong Form; FERC Urges Tariff Changes
On November 30, 2023, the Commission denied a waiver request and a request for remedial relief from Ridgeview Solar LLC (“Ridgeview Solar”). Ridgeview Solar had sought a waiver or remedial relief from the procedural deadline in section 212.4 of the PJM Interconnection, L.L.C. (“PJM”) Open Access Transmission Tariff (“Tariff”) to post security after the deadline outlined in the section.
FERC denies Muni Complaint on Proposed RNG Interconnection Request
On November 30, 2023, the Commission denied the Minnesota Municipal Power Agency’s (“MMPA”) complaint alleging that Northern Natural Gas Company (“Northern”) violated the Natural Gas Act (“NGA”) by refusing to execute an interconnection agreement for MMPA’s planned renewable natural gas (“RNG”) facility in Elk River, Minnesota (“Elk River Project”). The Commission denied MMPA’s complaint without prejudice because the complaint was unripe since Northern has yet to act on MMPA’s interconnection request.
FERC Partially Accepts Arizona Public Service Company’s Proposed Interconnection Queue Reforms
On September 29, 2023, FERC accepted part of Arizona Public Service Company’s (“APS”) proposed interconnection queue reforms to transition from a first come, first served cluster study process to a first ready, first served cluster study process. Generally, FERC accepted APS’s proposals that would prevent speculative projects from moving through the queue, while rejecting proposals that were not consistent with or superior to the pro forma Large Generator Interconnection Procedures (“LGIP”). APS’s interconnection queue reform proposal was submitted before FERC issued Order No. 2023; the approved reforms do not constitute APS’s Order No. 2023 compliance filing and are based on FERC’s currently effective pro forma LGIP.