Photo of Antonia Douglas

On October 1, 2025, the Federal Energy Regulatory Commission issued a final rule revising 53 regulations to include conditional sunset provision in response to the April 2025 Executive Order titled “Zero-Based Regulatory Budgeting to Unleash American Energy.” FERC, along with nine other agencies, was required to establish one-year

On September 9, 2025, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) on remand from the U.S. Supreme Court upheld FERC’s order granting Broadview Solar, LLC’s (“Broadview”) hybrid solar and battery project qualifying facility (“QF”) status based on FERC’s interpretation of the Public Utility Regulatory Policies Act of 1978 (“PURPA”). Specifically, even without the benefit of Chevron deference (discussed below), the D.C. Circuit reaffirmed FERC’s interpretation that PURPA’s 80 MW statutory size limitation should be applied using the capacity a QF can “send out” to the grid, even if the facilities have a higher aggregate generating capacity.

On July 15, 2025, FERC initiated an investigation, pursuant to section 206 of the Federal Power Act (“FPA”), to assess whether the Western Electricity Coordinating Council’s (“WECC”) soft price cap on spot market energy sales should be eliminated. FERC preliminarily concluded that the WECC soft price cap is no longer just and reasonable because of changes in the circumstances in the WECC market, and thus proposed its elimination pending the results of the investigation. FERC requested that interested parties submit comments within 30 days of its order (i.e., by August 14, 2025). FERC expects to issue an order on the results of its investigation by December 30, 2025.

On June 26, 2025, FERC upheld PJM Interconnection, L.L.C.’s (PJM) proposal to revise its Capacity Performance Quantifiable Risk (CPQR) Offer Cap. Several public interest organizations and PJM’s Independent Market Monitor (Market Monitor) filed requests for rehearing, arguing that PJM’s tariff changes did not adequately differentiate between costs directly related to capacity commitments and those incurred for other reasons, potentially leading to unfair rates. FERC disagreed, stating that PJM’s definition of CPQR provides a clear principle for identifying relevant costs and prevents sellers from inflating offer caps with unrelated expenses. The Commission emphasized that the review process by PJM and the Market Monitor ensures adherence to this principle, maintaining fair and competitive market practices.

On May 27, 2025, FERC addressed arguments raised on rehearing of a January 30, 2025 order, which accepted the Midcontinent Independent System Operator, Inc.’s (“MISO”) proposal to modify its generator interconnection study process by implementing a queue cap and exemptions to that cap (the “Queue Cap Order”). In doing so, FERC reaffirmed that MISO’s proposed queue cap and exemptions align with Order No. 2003’s independent entity variations for regional transmission organizations and independent system operators.

On April 24, 2025, FERC denied NGO Transmission, Inc.’s (“NGO Transmission”) application under 7(b) of the Natural Gas Act (“NGA”) to abandon its jurisdictional facilities and reclassify them from jurisdictional transmission facilities to non-jurisdictional local distribution facilities. FERC concluded that NGO Transmission’s facilities do not directly serve end-use customers in

On April 8, 2025, President Donald Trump issued the Strengthening the Reliability and Security of the U.S. Electric Grid executive order aimed at ensuring adequate and reliable electric generation in the U.S., meeting growing electricity demand being driven by technological advancements (e.g., data centers), and addressing the national energy emergency declared on January 20, 2025. The executive order also intends to help ensure that the electrical grid leverages all available power generation resources, with a particular emphasis on secure resources that have redundant fuel supplies to support extended operations.

On March 27, 2025, FERC approved Southwest Power Pool, Inc.’s (SPP) tariff revisions to remove the opportunity for resources that self-commit during the Reliability Unit Commitment Process (RUC) to avoid contributing to RUC system-wide make-whole payments. In doing so, FERC found the revisions are consistent with cost causation principles.

On March 30, 2025, FERC approved revisions to Southwest Power Pool, Inc.’s (“SPP”) Open Access Transmission Tariff (“Tariff”) and Governing Documents to allow nine entities (“Expansion Members”) in the Western Interconnection to join SPP’s Regional Transmission Organization (“RTO”) as transmission-owning members (“RTO West”), on the condition that SPP submit compliance