On May 19, 2022, FERC issued a Notice of Proposed Rulemaking (“NOPR”) to establish a rule that would require natural gas pipelines to submit all supporting statements, schedules, and workpapers in native format, with all links and formulas intact, when filing a Natural Gas Act (“NGA”) section 4 rate case. FERC issued the NOPR in response to a petition from several national gas trade associations, which argued that FERC’s current policy of permitting certain supporting documents to be filed in non-native format does not ensure that FERC staff and stakeholders have access to all information required to perform routine rate analyses. Comments on the NOPR are due June 17, 2022.
Continue Reading FERC Proposes Changes to Filing and Reporting Requirements for NGA Section 4 Rate Cases
Katherine O'Konski
PJM Will File Interconnection Queue Reform Proposal at FERC in May 2022
On April 27, 2022, members of the PJM Interconnection, L.L.C. (“PJM”) Members Committed voted in favor of a suite of tariff reforms that PJM states will revamp and improve its generator interconnection process. In a press release issued that same day, PJM stated that the changes will create a faster, more efficient interconnection process, allowing PJM to better handle the influx of interconnection requests PJM has seen in recent years and will continue seeing into the future. In a press release dated April 28, 2022, PJM reported that it plans to file the proposal with FERC in May 2022.
Continue Reading PJM Will File Interconnection Queue Reform Proposal at FERC in May 2022
Declining to Propose a Generic Solution, FERC Directs RTOs/ISOs to File Reports on System Needs
On April 21, 2022, FERC directed each regional transmission organization/independent system operator (“RTO/ISO”) to submit information related to their wholesale markets, including how changing resource mixes and load profiles are affecting system needs. FERC stated it will review the reports and any public comments filed to determine whether further action is appropriate.
Continue Reading Declining to Propose a Generic Solution, FERC Directs RTOs/ISOs to File Reports on System Needs
Summary of FERC’s April 2022 NOPR on Transmission Planning, Cost Allocation, and Generator Interconnection
On April 21, the Federal Energy Regulatory Commission (FERC or Commission) released its Notice of Proposed Rulemaking (NOPR) to reform its policies regarding Regional Transmission Planning and Cost Allocation. The NOPR follows from an Advanced Notice of Proposed Rulemaking (ANOPR) on these reforms, which FERC issued in July 2021. Representing FERC’s most significant action on transmission planning and cost allocation in more than a decade, the NOPR outlines six major proposals:
Continue Reading Summary of FERC’s April 2022 NOPR on Transmission Planning, Cost Allocation, and Generator Interconnection
FERC Approves Civil Penalties for Alleged Violations of CAISO and PJM Market Rules
On March 28, 2022 and March 29, 2022, FERC issued two orders approving stipulation and consent agreements between FERC’s Office of Enforcement and Dynegy Marketing and Trade, LLC (“Dynegy”) and Constellation NewEnergy Inc. (“Constellation”), respectively. Among other things, Dynegy agreed to pay a $450,000 civil penalty for alleged violations of PJM Interconnection, L.L.C. (“PJM”) capacity tariff requirements, and Constellation agreed to pay a $2.4 million civil penalty for alleged violations of California Independent System Operator Corp. (“CAISO”) resource adequacy tariff requirements.
Continue Reading FERC Approves Civil Penalties for Alleged Violations of CAISO and PJM Market Rules
FERC Reverses Prior Order, Allows NYISO to Prioritize Entry of Zero Emission Resources in New York’s Capacity Market
On February 17, 2022, FERC set aside its September 2020 order rejecting the New York Independent System Operator Corporations (“NYISO’s”) tariff revisions to the “Part A Test,” a component of NYISO’s buyer-side mitigation (“BSM”) rules. The now-approved changes on rehearing permit NYISO to prioritize entry of renewable resources, battery storage, and other zero emission resources (“Public Policy Resources”) in New York’s Installed Capacity (“ICAP”) Market, rather than prioritizing new resources purely on a least-cost basis. FERC also ordered NYISO to submit a compliance filing within 30 days proposing a new effective date for its tariff revisions. Commissioner James Danly issued a separate dissenting statement, arguing that the reversal was a “cynical attempt” to preference renewable resources. Commissioner Mark Christie issued a separate concurring statement, agreeing with the majority that the result was just and reasonable in NYISO after concluding that the costs of the change would be confined to New York.
Continue Reading FERC Reverses Prior Order, Allows NYISO to Prioritize Entry of Zero Emission Resources in New York’s Capacity Market
D.C. Circuit Grants Emergency Petition for Stay of FERC’s Order Terminating Killingly Energy Center’s ISO-NE Capacity Commitments
On February 4, 2022, the United States Court of Appeals for the District of Columbia Circuit (“DC Circuit”) issued a per curiam order granting NTE Connecticut, LLC’s (“NTE”) petition for issuance of a writ under the All Writs Act to stay a FERC order issued January 3, 2022 (“January 3 Order”). The January 3 Order terminated the Killingly Energy Center’s capacity commitments in the ISO-New England, Inc. (“ISO-NE”) capacity market. The DC Circuit’s order stays FERC’s January 3 Order until 30 days after FERC resolves NTE’s pending request for rehearing of the January 3 Order. The DC Circuit’s order also states that an opinion will follow in due course. As a result of the DC Circuit’s order, ISO-NE ran its Forward Capacity Auction on February 7, 2022 as scheduled but after “unwind[ing] the actions it had taken to terminate Killingly.” ISO-NE has stated that it will update the auction results if FERC confirms Killingly’s termination.
Continue Reading D.C. Circuit Grants Emergency Petition for Stay of FERC’s Order Terminating Killingly Energy Center’s ISO-NE Capacity Commitments
On Remand, FERC Reverses Prior Approval of PJM 10% Net CONE Adder
On January 20, 2022, FERC issued an order on remand from the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) directing PJM Interconnection, L.L.C. (“PJM”) to remove provisions from its Tariff that applied a 10 percent adder to the energy and ancillary services (“E&AS”) offset in PJM’s net Cost of New Entry (“CONE”) calculation. FERC acknowledged that energy market rules permit generators to increase their offers into the energy market by 10 percent above estimated costs. That fact alone, FERC concluded, does not justify application of the 10 percent adder to the E&AS offset in the Net CONE calculation used to establish the Variable Resource Requirement Curve (“VRR Curve”). Moreover, FERC concluded, PJM failed to present sufficient evidence to support inclusion of the 10 percent adder. FERC directed PJM to remove the 10 percent adder from its VRR Curve determination for the 2023-2024 Base Residual Auction (“BRA”) and subsequent auctions. FERC previously directed PJM to delay the start of the 2023-2024 BRA (see January 18, 2022 edition of the WER). In the January 20 order, FERC stated its expectation that PJM propose an amended BRA schedule that would provide it adequate time to remove the 10 percent adder from its Tariff. Commissioner James Danly issued a separate dissenting statement.
Continue Reading On Remand, FERC Reverses Prior Approval of PJM 10% Net CONE Adder
FERC Reverses Certain Changes to PJM Reserve Market in Voluntary Remand Proceeding
On December 22, 2021, FERC issued an order on voluntary remand from the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) directing changes to PJM Interconnection, L.L.C.’s (“PJM’s”) reserve market design. FERC’s December 22 order reverses certain changes it previously ordered in May 2020 (“May 2020 Order”). The December 22 order affirmed FERC’s decision in the May 2020 Order to accept PJM’s proposal to consolidate its Tier 1 and Tier 2 Synchronized Reserve Products. However, the December 22 order required PJM to revert back to its currently-effective Reserve Penalty Factors, two-step Operating Reserve Demand Curve (“ORDC”), and a backward-looking Energy and Ancillary Services (“E&AS”) Offset. FERC directed PJM to apply the backward-looking E&AS Offset to the 2023/24 Base Residual Auction (“BRA”), which was previously scheduled to run in January 2022, notwithstanding any resulting delay to the auction schedule. FERC required PJM to submit a revised BRA schedule on compliance. Commissioner Christie issued a concurring opinion, and Commissioner Danly dissented in part.
Continue Reading FERC Reverses Certain Changes to PJM Reserve Market in Voluntary Remand Proceeding
FERC Approves $300,000 Settlement Between ReliabilityFirst and Ohio Valley Electric Corp. for Violations of NERC Reliability Standards
On November 26, 2021, FERC issued a notice stating that it would not review a Notice of Penalty filed by the North American Electric Reliability Corporation (“NERC”) against Ohio Valley Electric Corporation (“OVEC”). FERC’s November 26 notice effectively approves a $300,000 settlement between OVEC and the regional reliability entity, ReliabilityFirst Corporation (“RF”), for violations of NERC reliability standards FAC-003-4 R2 and FAC-003-4 R6, which address vegetation management. The settlement followed a 4.5-hour outage to one of OVEC’s 345 kV transmission lines in September 2018 that resulted when contact with a cedar tree growing in close proximity tripped the line out of service. OVEC neither admitted nor denied the violations, but agreed to the assessed $300,000 penalty.
Continue Reading FERC Approves $300,000 Settlement Between ReliabilityFirst and Ohio Valley Electric Corp. for Violations of NERC Reliability Standards