On March 12, 2024, the U.S. Court of Appeals for the Third Circuit upheld a prospective rule change to PJM Interconnection, L.L.C.’s (“PJM”) annual capacity auction but struck down attempts by PJM and FERC to apply the rule change to the ongoing auction held in December 2022. Although the rule change permits PJM to adjust the Locational Deliverability Area (“LDA”) Reliability Requirement downward to reflect the lack of participation in the December 2022 auction by certain resources to correct for distortions to the auction results, the Third Circuit held that FERC could not permit the change to go into effect in the middle of an ongoing auction.Continue Reading Third Circuit Upholds PJM Capacity Market Change but Prevents Retroactive Application
Steven G. Boughton
Troutman Pepper Summary of FERC Order No. 2023-A on Generator Interconnections
Executive Summary
On March 21, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 2023-A (Final Rule), which reaffirmed aspects of Order No. 2023 — the Commission’s landmark order updating its generator interconnection procedures. As detailed further in this summary, the Commission largely upheld Order No. 2023, including some of the more controversial aspects of the order, such as penalties and the transmission capacity “heat map,” and provided further clarity on other aspects.Continue Reading Troutman Pepper Summary of FERC Order No. 2023-A on Generator Interconnections
Department of Energy Issues Final Guidance on National Interest Electric Transmission Corridor Designation
On December 19, 2023, the Department of Energy (“DOE”) Grid Deployment Office released final guidance on how it will designate National Interest Electric Transmission Corridors (“NIETC”) pursuant to Section 216(a) of the Federal Power Act (“FPA”) and opened the first submission window for public participation and recommendations. The guidance explains that NIETCs will be narrow geographic areas where DOE has identified present or expected transmission capacity constraints or congestion that adversely affects consumers. Designation as a NIETC opens federal funding and financing opportunities, pursuant to the Infrastructure Investment and Jobs Act (“IIJA”) and the Inflation Reduction Act (“IRA”) and conveys eminent domain rights to developers in certain circumstances where FERC is authorized to permit and site the project. Public comments and recommendations are due February 2, 2024.Continue Reading Department of Energy Issues Final Guidance on National Interest Electric Transmission Corridor Designation
FERC Conditionally Approves CAISO Market Expansion
On December 20, 2023, FERC approved the California Independent System Operator Corporation’s (“CAISO”) proposal to establish the Extended Day Ahead Market (“EDAM”), which allows external Balancing Authority Areas (“BAAs”) to participate in CAISO’s day-ahead market. FERC also approved CAISO’s Day Ahead Market Enhancements (“DAME”) proposal, which establishes two new day-ahead market products: Imbalance Reserves and Reliability Capacity. FERC approved the CAISO’s proposals but rejected the proposed EDAM access charge without prejudice. CAISO must submit a compliance filing addressing FERC’s conditions within sixty (60) days of the Order.Continue Reading FERC Conditionally Approves CAISO Market Expansion
D.C. Circuit Upholds PJM Tariff Changes to Planning of Asset Management and End of Life Projects
On November 17, 2023, the U.S. Court of Appeals of the District of Columbia Circuit (“D.C. Circuit”) denied petitions challenging FERC’s approval of recent changes to the PJM Interconnection, L.L.C.’s (“PJM”) Open Access Transmission Tariff. The changes permit Transmission Owners in PJM to plan for “asset management projects” and certain End of Life (“EOL”) projects without satisfying PJM regional planning criteria. The D.C. Circuit also dismissed certain petitions for lack of standing.Continue Reading D.C. Circuit Upholds PJM Tariff Changes to Planning of Asset Management and End of Life Projects
FERC Staff Issues Winter Reliability Assessment Report
On November 16, 2023, FERC staff issued the 2023-2024 Winter Energy Market and Electric Reliability Assessment report, projecting trends and identifying considerations for energy markets and electric reliability for the upcoming winter (December through February). The report focuses on weather outlook, the state of the natural gas and electricity markets, and initiatives implemented in the wake of Winter Storm Elliott.Continue Reading FERC Staff Issues Winter Reliability Assessment Report
Department of Energy Releases Triennial National Transmission Needs Study
On October 20, 2023, the U.S. Department of Energy (“DOE”) released the National Transmission Needs Study, a triennial report that assesses electric transmission capacity constraints and congestion on a national scale. While similar to previously issued triennial reports, the 2021 Bipartisan Infrastructure Law expanded the study’s scope to also consider anticipated future transmission constraints and congestion. The study assessed needs through 2040 and revealed a pressing need for additional transmission infrastructure to promote reliability in the face of a shifting resource mix, with the largest benefits stemming from increases to interregional transfer capacity.Continue Reading Department of Energy Releases Triennial National Transmission Needs Study
FERC Directs NERC to Develop Reliability Standards for Inverter Based Resources
On October 19, 2023, FERC issued a final rule directing the North American Reliability Corporation (“NERC”) to develop or modify reliability standards to address reliability concerns attributable to inverter-based resources (“IBRs”)—i.e., solar photovoltaic, wind, fuel cell, and battery storage resources. FERC explained that the current reliability standards were designed for a grid mostly comprised of synchronous resources, where all generators are operating at the same frequency across the grid. In recent years, there has been a substantial increase in renewable generation, such as wind and solar, which is largely nonsynchronous, meaning generators that do not operate at the same frequency as the synchronized grid. Nonsynchronous resources are often programmed to trip offline during system disturbances, resulting in the potential loss of significant amounts of generation at one time. FERC issued this order in response to the “unprecedented proportion of nonsynchronous resources” expected to connect to the grid in the coming years and the “material impact” of IBRs on the Bulk Power System, including at least 12 documented events where IBRs responded “unexpectedly and adversely” to normally cleared line faults and the largest IBR-related disturbance NERC has ever recorded. The rule directs NERC to submit the updated standards by November 4, 2026.Continue Reading FERC Directs NERC to Develop Reliability Standards for Inverter Based Resources
Department of Energy Proposes New Program to Streamline Federal Authorizations to Site Interstate Transmission Projects
On August 10, 2023 in response to incentives made available through the Bipartisan Infrastructure Law and the Inflation Reduction Act, the U.S. Department of Energy (“DOE”) proposed reforms to its regulations governing the coordination of Federal authorizations for the development of interstate, onshore electric transmission facilities and to establish the Coordinated Interagency Transmission Authorizations and Permits Program (“CITAP Program”). The main goal of the CITAP Program, which will be administered by DOE’s Grid Deployment Office, is to “reduce the time required for transmission project developers to receive decisions on Federal authorizations for transmission projects.” Public comments are due by 11:59pm ET on October 2, 2023.Continue Reading Department of Energy Proposes New Program to Streamline Federal Authorizations to Site Interstate Transmission Projects
D.C. Circuit Backs FERC in New York Cost Allocation Dispute, Giving FERC Broad Deference under the Rule of Reason
On July 7, 2023, the U.S. Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) issued an opinion rejecting petitioner Hecate Energy Green County 3 LLC’s (“Hecate”) claim that the New York Independent System Operator (“NYISO”) tariff did not contain sufficient detail to put it on notice that NYISO would assess network upgrade costs resulting from non-jurisdictional projects. Instead, the Court agreed with FERC that because its tariff gave “fair notice,” NYISO “had not impermissibly adopted a practice that was not in its tariff.”Continue Reading D.C. Circuit Backs FERC in New York Cost Allocation Dispute, Giving FERC Broad Deference under the Rule of Reason