On May 3, 2023, a divided FERC voted 3-1 to deny a widely-supported complaint by multiple utilities in the Southwest Power Pool (“SPP”) region arguing that the absence of the new 15% generation Planning Reserve Margin (“Reserve Margin”) from the SPP tariff rendered that tariff unjust and unreasonable.  The Reserve Margin dictates exactly how much electric generating capacity load-serving utilities must own or have under contract to serve customers.  The complaining utilities argued that customers in SPP could be harmed by the costs associated with the rapid increase in the Reserve Margin with little corresponding reliability benefit and asked FERC to keep closer tabs on the process.  The utilities’ request for additional FERC oversight was opposed only by SPP itself.  As a result of the decision, SPP is free to change the Reserve Margin without any oversight by FERC or approval by a single state commission.   FERC further held that a complaint alleging that a key rate is missing from a tariff in violation of section 205 of the Federal Power Act and the Commission’s Rule of Reason fails to state a claim upon which relief could be granted. 

Continue Reading Divided FERC Announces Hands-Off Approach to Capacity Issues in SPP, Raises Questions About Tariff Detail Complaints

On March 16, 2023, FERC granted a petition declaring that, should it issue orders pursuant to Sections 210 and 211 of the Federal Power Act (“FPA”), which would be required for a prospective project to interconnect Puerto Rico’s transmission system to the U.S. mainland bulk electric system, such orders would “not render Puerto Rico’s electric utilities ‘public utilities’ under section 201(e) of the FPA. However, FERC reserved the right to make a fact-specific determination at the time any application for such interconnection is sought and further affirmed that, regardless of “public utility” status, FERC would retain jurisdiction over Puerto Rico’s electric utilities pursuant to sections 210, 211, 211A, 212, and 215 of the FPA.

Continue Reading FERC Confirms that Orders Under Sections 210 and 211 of the Federal Power Act Would Not Generally Confer “Public Utility” Jurisdiction over Puerto Rico’s Electric Utilities

On February 10, 2023, FERC approved the Western Resource Adequacy Program (“WRAP”) proposed by the Western Power Pool (“WPP”). The voluntary program commits participants to demonstrate prior to a given Winter or Summer season that they have sufficient capacity to meet a required planning reserve margin and have reserved 75% of the transmission to deliver that capacity to load. The WRAP also allows those who are short on capacity to call on the excess capacity of other participants during critical periods. The Southwest Power Pool, Inc. will run the operations of the program, which became effective January 1, 2023, under the oversight of WPP.

Continue Reading FERC Approves Regional Resource Adequacy Program in the Western Interconnection

On January 19, 2023, FERC established that a facility’s classification as transmission or distribution under criteria established in the Southwest Power Pool, Inc.’s (“SPP”) Open Access Transmission Tariff (“Tariff”) can be overcome in a challenge at the Commission if the protestors provide sufficient evidence to call into question the classification under the Tariff criteria. FERC found that once protestors present evidence that the facilities are distribution under FERC’s seven-factor test, the burden of proof shifts back to the filing transmission provider and transmission owner seeking a specific classification under Section 205 of the Federal Power Act to demonstrate its proposed classification under FERC’s seven-factor test. FERC found that GridLiance High Plains, LLC (“GridLiance”), as the applicable transmission owner, failed to carry this burden to demonstrate its facilities at issue were transmission facilities after such a challenge.

Continue Reading FERC Affirms Burden of Persuasion Rests on Proponents of Transmission Asset Classifications under FERC’s Seven-Factor Test, Notwithstanding Tariff Classifications

On December 16, 2022, FERC again rejected the Midcontinent Independent System Operator Inc. (“MISO”) proposal for Transmission Owners to self-fund Necessary Upgrades to connect Merchant High Voltage Direct Current (“HVDC”) transmission lines into MISO and addressed arguments on rehearing. Commissioner Danly dissented and Commissioner Christie concurred in separate statements. Chairman Glick did not participate.

Continue Reading On Rehearing FERC Again Rejects MISO Proposal for Transmission Owners to Self-Fund Necessary Upgrades to Connect Merchant HVDC Lines

On November 18, 2022, FERC accepted a September 19, 2022 proposal from the California Independent System Operator (“CAISO”) to correct “excessively high” payments being made to electric storage resources that are forced to discharge to meet state of charge requirements when providing ancillary services. The proposal also aims to encourage those resources to reflect opportunity costs through their ancillary services bids rather than energy bids.

Continue Reading FERC Accepts CAISO Proposal to Correct Payment Overcollections by Storage Resources

On November 17, 2022, FERC approved an application authorizing Commonwealth LNG, LLC (“Commonwealth”) to site, construct, and operate a liquified natural gas (“LNG”) export terminal in Cameron Parish, Louisiana. The LNG facility’s authorization drew concurring opinions from four of the Commissioners.

Continue Reading FERC Authorizes Commonwealth LNG Export Facility

On November 2, 2022, FERC denied a complaint brought by the Iowa Coalition for Affordable Transmission (“ICAT”) alleging that ITC Midwest, LLC’s (“ITC Midwest”) capital structure, with a targeted 60%-40% equity-to-debt ratio, is unjust and unreasonable. FERC found that ICAT failed to demonstrate that ITC Midwest’s use of its actual capital structure to determine its equity ratio is unjust and unreasonable and that ICAT’s reliance on prior FERC precedent was misplaced. Given these findings, FERC declined to address ICAT’s arguments for a 53% equity ratio.

Continue Reading FERC Denies Complaint Against ITC Midwest’s Capital Structure

On August 31, 2022, FERC issued two orders regarding two proposals to revise the Midcontinent Independent System Operator’s (“MISO”) resource adequacy requirements. In the first order, FERC accepted MISO’s proposal to move to seasonal resource adequacy requirements rather than a single requirement based on the summer peak. MISO proposed this seasonal resource adequacy construct to address significant increases in emergency events that occur year-round, driven by factors including generation retirements, reliance on intermittent resources, outages resulting from extreme weather events, and declining excess reserve margin. MISO will implement the new seasonal resource adequacy construct in the next Planning Resource Auction (“Auction”) to be held in April 2023. In the second order, FERC rejected MISO’s proposal to require a Minimum Capacity Obligation for participants in MISO’s Auction (“MCO Proposal”).
Continue Reading FERC Approves MISO Seasonal Resource Adequacy Requirements but Rejects Minimum Capacity Obligation

On July 28, 2022, FERC proposed changes to its Uniform System of Accounts (“USofA”) in response to the growth of non-hydro renewable generation such as wind, solar, and storage and to codify accounting for renewable energy credits (“RECs”). FERC’s Notice of Proposed Rulemaking (“NOPR”) follows a Notice of Inquiry issued in January 2021 seeking comment on the appropriate accounting treatment for certain renewable energy assets (see January 28, 2021 edition of the WER). Comments on the NOPR are due 45 days from its publication in the Federal Register.
Continue Reading FERC Proposes Revised Accounting Rules to Address Renewables