On August 10, 2023 in response to incentives made available through the Bipartisan Infrastructure Law and the Inflation Reduction Act, the U.S. Department of Energy (“DOE”) proposed reforms to its regulations governing the coordination of Federal authorizations for the development of interstate, onshore electric transmission facilities and to establish the Coordinated Interagency Transmission Authorizations and Permits Program (“CITAP Program”). The main goal of the CITAP Program, which will be administered by DOE’s Grid Deployment Office, is to “reduce the time required for transmission project developers to receive decisions on Federal authorizations for transmission projects.” Public comments are due by 11:59pm ET on October 2, 2023.
Steven G. Boughton
D.C. Circuit Backs FERC in New York Cost Allocation Dispute, Giving FERC Broad Deference under the Rule of Reason
On July 7, 2023, the U.S. Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) issued an opinion rejecting petitioner Hecate Energy Green County 3 LLC’s (“Hecate”) claim that the New York Independent System Operator (“NYISO”) tariff did not contain sufficient detail to put it on notice that NYISO would assess network upgrade costs resulting from non-jurisdictional projects. Instead, the Court agreed with FERC that because its tariff gave “fair notice,” NYISO “had not impermissibly adopted a practice that was not in its tariff.”…
D.C. Circuit Addresses Appeals of Rehearings Denied by Operation of Law
In its May 26, 2023 opinion in Sierra Club v. Federal Energy Regulatory Commission (an article on the rest of the opinion regarding FERC’s environmental review of the Mountain Valley Pipeline can be found here), the United States Court of Appeals for the District of Columbia Circuit addressed challenges to its jurisdiction to hear appeals of Commission rehearing orders when they are denied by operation of law and the Commission subsequently modifies the underlying order after said denial.…
Continue Reading D.C. Circuit Addresses Appeals of Rehearings Denied by Operation of Law
D.C. Circuit Finds FERC Failed to Justify Not Preparing a Supplemental EIS for Mountain Valley Pipeline
On May 26, 2023, the United States Court of Appeals for the District of Columbia Circuit issued an opinion in Sierra Club v. Federal Energy Regulatory Commission largely denying challenges to several FERC orders authorizing the resumption of construction of Mountain Valley Pipeline (“MVP”) but remanded, without vacatur, all but one of the orders on review insofar as FERC failed to adequately explain its decision not to prepare a supplemental Environmental Impact Statement (“EIS”) for MVP. (See related article on the Court’s finding with regard to hearing appeals of FERC’s rehearing orders, here).…
Divided FERC Announces Hands-Off Approach to Capacity Issues in SPP, Raises Questions About Tariff Detail Complaints
On May 3, 2023, a divided FERC voted 3-1 to deny a widely-supported complaint by multiple utilities in the Southwest Power Pool (“SPP”) region arguing that the absence of the new 15% generation Planning Reserve Margin (“Reserve Margin”) from the SPP tariff rendered that tariff unjust and unreasonable. The Reserve Margin dictates exactly how much electric generating capacity load-serving utilities must own or have under contract to serve customers. The complaining utilities argued that customers in SPP could be harmed by the costs associated with the rapid increase in the Reserve Margin with little corresponding reliability benefit and asked FERC to keep closer tabs on the process. The utilities’ request for additional FERC oversight was opposed only by SPP itself. As a result of the decision, SPP is free to change the Reserve Margin without any oversight by FERC or approval by a single state commission. FERC further held that a complaint alleging that a key rate is missing from a tariff in violation of section 205 of the Federal Power Act and the Commission’s Rule of Reason fails to state a claim upon which relief could be granted. …
FERC Confirms that Orders Under Sections 210 and 211 of the Federal Power Act Would Not Generally Confer “Public Utility” Jurisdiction over Puerto Rico’s Electric Utilities
On March 16, 2023, FERC granted a petition declaring that, should it issue orders pursuant to Sections 210 and 211 of the Federal Power Act (“FPA”), which would be required for a prospective project to interconnect Puerto Rico’s transmission system to the U.S. mainland bulk electric system, such orders would “not render Puerto Rico’s electric utilities ‘public utilities’ under section 201(e) of the FPA. However, FERC reserved the right to make a fact-specific determination at the time any application for such interconnection is sought and further affirmed that, regardless of “public utility” status, FERC would retain jurisdiction over Puerto Rico’s electric utilities pursuant to sections 210, 211, 211A, 212, and 215 of the FPA.…
FERC Approves Regional Resource Adequacy Program in the Western Interconnection
On February 10, 2023, FERC approved the Western Resource Adequacy Program (“WRAP”) proposed by the Western Power Pool (“WPP”). The voluntary program commits participants to demonstrate prior to a given Winter or Summer season that they have sufficient capacity to meet a required planning reserve margin and have reserved 75% of the transmission to deliver that capacity to load. The WRAP also allows those who are short on capacity to call on the excess capacity of other participants during critical periods. The Southwest Power Pool, Inc. will run the operations of the program, which became effective January 1, 2023, under the oversight of WPP.…
Continue Reading FERC Approves Regional Resource Adequacy Program in the Western Interconnection
FERC Affirms Burden of Persuasion Rests on Proponents of Transmission Asset Classifications under FERC’s Seven-Factor Test, Notwithstanding Tariff Classifications
On January 19, 2023, FERC established that a facility’s classification as transmission or distribution under criteria established in the Southwest Power Pool, Inc.’s (“SPP”) Open Access Transmission Tariff (“Tariff”) can be overcome in a challenge at the Commission if the protestors provide sufficient evidence to call into question the classification under the Tariff criteria. FERC found that once protestors present evidence that the facilities are distribution under FERC’s seven-factor test, the burden of proof shifts back to the filing transmission provider and transmission owner seeking a specific classification under Section 205 of the Federal Power Act to demonstrate its proposed classification under FERC’s seven-factor test. FERC found that GridLiance High Plains, LLC (“GridLiance”), as the applicable transmission owner, failed to carry this burden to demonstrate its facilities at issue were transmission facilities after such a challenge.…
On Rehearing FERC Again Rejects MISO Proposal for Transmission Owners to Self-Fund Necessary Upgrades to Connect Merchant HVDC Lines
On December 16, 2022, FERC again rejected the Midcontinent Independent System Operator Inc. (“MISO”) proposal for Transmission Owners to self-fund Necessary Upgrades to connect Merchant High Voltage Direct Current (“HVDC”) transmission lines into MISO and addressed arguments on rehearing. Commissioner Danly dissented and Commissioner Christie concurred in separate statements. Chairman Glick did not participate.…
FERC Accepts CAISO Proposal to Correct Payment Overcollections by Storage Resources
On November 18, 2022, FERC accepted a September 19, 2022 proposal from the California Independent System Operator (“CAISO”) to correct “excessively high” payments being made to electric storage resources that are forced to discharge to meet state of charge requirements when providing ancillary services. The proposal also aims to encourage those resources to reflect opportunity costs through their ancillary services bids rather than energy bids.…
Continue Reading FERC Accepts CAISO Proposal to Correct Payment Overcollections by Storage Resources