On December 12, 2023, FERC staff offered information and recommendations to help registered entities (i.e., users, owners, and operators of the bulk electric system) improve their compliance with mandatory Critical Infrastructure Protection (“CIP”) reliability standards and their overall cybersecurity postures (the “Report”). The recommendations are based on FERC staff’s non-public CIP audits of U.S.-based North American Electric Reliability Corporation (“NERC”) registered entities during Fiscal Year 2023, which included the participation of NERC and the regional entities. FERC staff found that registered entities generally met the mandatory requirements of the CIP Standards, although potential noncompliance and security risks remained. FERC staff also identified and made recommendations concerning other voluntary best practices that could improve cybersecurity. FERC staff explained that the CIP standards aim to mitigate cybersecurity and physical security risks to the bulk electric system’s facilities and equipment. The Commission approved the first set of eight mandatory CIP standards on cybersecurity on January 28, 2008, and has since revised the standards to respond to emerging cybersecurity issues. FERC began its CIP standards audit program for registered entities in 2016 and has conducted CIP audits each year since.
FERC Practice
D.C. Circuit Upholds PJM Tariff Changes to Planning of Asset Management and End of Life Projects
On November 17, 2023, the U.S. Court of Appeals of the District of Columbia Circuit (“D.C. Circuit”) denied petitions challenging FERC’s approval of recent changes to the PJM Interconnection, L.L.C.’s (“PJM”) Open Access Transmission Tariff. The changes permit Transmission Owners in PJM to plan for “asset management projects” and certain End of Life (“EOL”) projects without satisfying PJM regional planning criteria. The D.C. Circuit also dismissed certain petitions for lack of standing.
Unlocking U.S. Transmission Upgrades – Are We on the Cusp of Real Progress?
Bridging the Gap Between Planning and Permitting
In recent decades, the U.S. has not been able to construct the volume of high-voltage backbone transmission facilities needed to support the country’s move to a ‘greener’ power system. The inability to build sufficient transmission infrastructure thwarts customer demands for a greener power mix.
In this report, we offer perspectives from a range of transmission experts about where the major roadblocks exist, and the latest regulatory and legal changes that promise to bring greater unity between the divergent federal planning and state siting and permitting processes. These changes provide hope that the U.S. can bridge the gaps that have delayed much-needed upgrades to the transmission system.
FERC Finds Dominion LNG Back-up Fuel Project Satisfies Hinshaw Exemption Under the NGA
On November 16, 2023, FERC granted Virginia Electric and Power Company d/b/a Dominion Energy Virginia’s (“Dominion”) petition requesting the Commission declare that Dominion’s planned liquefied natural gas (“LNG”) production, storage, and regasification facility (“Back-up Fuel Project” or “Project”) in Greensville County, Virginia would be exempt from the Commission’s jurisdiction under section 7 of the Natural Gas Act (“NGA”). In so doing, FERC determined the Project satisfied the “Hinshaw Exemption” under NGA section 1(c).
FERC Staff Issues Winter Reliability Assessment Report
On November 16, 2023, FERC staff issued the 2023-2024 Winter Energy Market and Electric Reliability Assessment report, projecting trends and identifying considerations for energy markets and electric reliability for the upcoming winter (December through February). The report focuses on weather outlook, the state of the natural gas and electricity markets, and initiatives implemented in the wake of Winter Storm Elliott.
FERC Partially Accepts Arizona Public Service Company’s Proposed Interconnection Queue Reforms
On September 29, 2023, FERC accepted part of Arizona Public Service Company’s (“APS”) proposed interconnection queue reforms to transition from a first come, first served cluster study process to a first ready, first served cluster study process. Generally, FERC accepted APS’s proposals that would prevent speculative projects from moving through the queue, while rejecting proposals that were not consistent with or superior to the pro forma Large Generator Interconnection Procedures (“LGIP”). APS’s interconnection queue reform proposal was submitted before FERC issued Order No. 2023; the approved reforms do not constitute APS’s Order No. 2023 compliance filing and are based on FERC’s currently effective pro forma LGIP.
FERC Approves CAISO Revisions to Wheeling Through Priority Tariff Provisions, Amending ATC Calculations to Account for Transmission Capacity Needed to Serve Native Load
On October 30, 2023, FERC accepted the California Independent System Operator Corporation’s (“CAISO”) revisions to its wheeling tariff provisions. The revised provisions allow external load serving entities to obtain, in advance, on a monthly and daily basis, rights to transmit electricity (also known as “wheeling”) through self-schedule priorities equal to the scheduling priority of CAISO demand. The revised provisions also update CAISO’s calculation of Available Transfer Capability (“ATC”).
PJM Files Capacity Market Overhaul for Resource Adequacy and Grid Reliability
On October 13, 2023, PJM Interconnection, L.L.C. (“PJM”) submitted two filings with FERC proposing revisions to its Open Access Transmission Tariff (“Tariff”) and its “Reliability Assurance Agreement” (“RAA”) designed to improve resource adequacy and grid reliability. PJM requested the Commission to accept both filings concurrently, with an effective date of December 12, 2023, so that PJM may implement the proposed reforms for the upcoming Base Residual Auction (“BRA”) associated with the 2025/2026 Delivery Year.
FERC Proposes Changes to Filing Requirements and Data Collection for Electric Quarterly Report
On October 19, 2023, FERC issued a Notice of Proposed Rule Making (“NOPR”) proposing various changes to its Electric Quarterly Report (“EQR”) filing requirements. According to FERC, the proposed changes are designed to update the data collection process, improve data quality, increase market transparency, decrease costs of preparing necessary data for submission, and streamline compliance with future filing requirements. The following is a summary of the primary reforms proposed.
FERC Accepts ISO-NE’s Proposal to Treat Electric Storage Facilities as Transmission-Only Assets
On October 19, 2023, FERC accepted ISO New England Inc.’s (“ISO-NE”) proposal to allow electric storage facilities to be planned and operated as transmission-only assets (“SATOAs”) to address system needs identified in the regional system planning process. FERC determined that the ISO-NE’s proposal established a just and reasonable framework for electric storage resources to be considered a transmission asset for regional planning purposes and thus be eligible for cost-based rate recovery.