On September 19, 2024, FERC approved Southwest Power Pool, Inc.’s (“SPP”) proposed tariff revisions allowing make-whole payments for incremental energy costs for offers affected by the incremental energy offer cost caps required by FERC’s Order No. 831. In doing so, FERC found that the tariff revisions appropriately provide an opportunity
D.C. Circuit Vacates FERC’s Approval of Transco’s Pipeline Expansion
On July 30, 2024, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) issued an opinion vacating and remanding FERC’s order approving Transcontinental Gas Pipe Line Company’s (“Transco”) Regional Energy Access Expansion Project (“Project”) determining that FERC failed to consider environmental consequences and evidence suggesting…
FERC Denies CPower’s Complaint Requesting Revisions to PJM’s Tariff Governing Curtailment Service Providers
On September 19, 2024, the Federal Energy Regulatory Commission (“FERC”) denied Enerwise Global Technologies, LLC’s (“CPower”) complaint against PJM Interconnection, LLC (“PJM”) alleging that PJM’s Open Access Transmission Tariff (“Tariff”) was unjust, unreasonable, and unduly discriminatory because it prevents Curtailment Service Providers (“CSP”) from using approved statistical sampling rules to…
Charging Ahead: Legal, Regulatory, and Operational Considerations for EV Infrastructure Development
The rapid growth in electric vehicle (EV) sales in the United States has created an urgent demand for robust EV charging infrastructure. The demand for EV charging infrastructure is driven by the need to ensure the benefits of EVs are fully realized. The EV industry has reached a critical tipping…
FERC Chief Accountant Proposes to Modify Transferability of Income Tax Credits
On September 12, 2024, FERC’s Chief Accountant issued a notice of proposed accounting release (“NOPAR”) to modify the transferability of income tax credits (“ITCs”) related to certain energy projects under the Inflation Reduction Act of 2022 (“IRA”), which allows entities to monetize such ITCs via transfers to independent third parties…
FERC Holds Workshop on Innovations & Efficiencies in Generator Interconnection Process, Seeks Comments
On September 10 and 11, 2024, FERC staff held a two-day workshop at its headquarters in Washington, DC on opportunities to further refine the generator interconnection queue process. Panelists and FERC staff discussed potential enhancements to transmission planning and processing interconnection requests over the course of six panels on discrete…
FERC Rejects Basin’s Special Rate for Crypto and Large Load Customers, Sparking Further Interest in “Large Load” Policy Discussions at FERC
On August 20, 2024, the Federal Energy Regulatory Commission (“FERC”) issued an order rejecting, without prejudice, a contested proposal from Basin Electric Power Cooperative (“Basin”) to establish special wholesale power sales rate schedules for cryptocurrency (“crypto”) operations and other new large loads. While FERC expressed sympathy for Basin’s concerns regarding its ability to serve expected load growth reliably and economically, FERC found that Basin failed to justify its proposal to treat crypto currency mining loads differently from other large loads and therefore rejected the differential rate proposal.
Eighth Circuit Applies FERC’s Filed Rate Doctrine to Reject Allegations that SPP Breached an Oral Contract Made During Winter Storm Uri
On August 5, 2024, the United States Court of Appeals for the Eighth Circuit (“Eighth Circuit”) denied Associated Electric Cooperative, Inc.’s (“AECI”) petition for review of a Federal Energy Regulatory Commission (“FERC”) order upholding FERC’s decision to exercise primary jurisdiction over emergency energy sales between Southwest Power Pool, Inc. (“SPP”) and AECI during Winter Storm Uri and FERC’s decision that SPP properly compensated AECI pursuant to SPP’s Open Access Transmission Tariff (“Tariff”). The Eighth Circuit denied the AECI’s petition and upheld FERC’s determination that AECI was appropriately compensated according to the existing tariff rates filed with FERC and, accordingly, rejected AECI’s claims that SPP had breached an alleged oral contract with SPP personnel made during the storm.
FERC Faults PJM for Failing to Execute Designated Entity Agreements, Establishes Hearing on Whether Remedial Actions Warranted
On July 25, 2024, FERC issued an order granting in part and denying in part a complaint raised by American Municipal Power, Inc., the People’s Counsel for the District of Columbia, and the PJM Industrial Customer Coalition (collectively, “Complainants”) against PJM Interconnection, L.L.C. (“PJM”) arguing, principally, that PJM violated Schedule 6 of the PJM Operating Agreement by failing to execute Designated Entity Agreements in all situations with each “Designated Entity,” or the entity designated to build transmission projects that PJM selects in the PJM Regional Transmission Expansion Plan (“RTEP”). FERC also granted in part and denied in part a separate request by PJM under section 206 of the Federal Power Act to revise Schedule 6 of the PJM Operating Agreement (the “PJM 206 Filing”) governing the RTEP process and associated requirements for Designated Entity Agreements. FERC established paper hearing procedures to develop a record to determine PJM’s responsibilities concerning Designated Entity Agreements for certain RTEP projects already in process and whether remedial actions are required to address the Operating Agreement violations.
D.C. Circuit Finds That Interconnection Customers are Responsible for Network Upgrade Costs
On July 19, 2024, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) issued an Order denying Tenaska Clear Creek Wind, LLC’s (“Clear Creek”) challenges to FERC’s orders allowing the allocation of costs for network upgrades. Southwest Power Pool, Inc. (“SPP”) assigned costs of more than $100 million to Clear Creek to pay for upgrades required on SPP’s system to accommodate the interconnection of Clear Creek’s wind turbine-powered electrical generation project (the “Project”).