On September 6, 2023, the Commission affirmed the determinations made in a May 4 Order, which found that Kimball Wind, LLC (“Kimball Wind”) was not entitled to reimbursement of funds paid to Western Area Power Administration (“WAPA”) for expansion of WAPA’s Kimball Substation, located in Kimball, Nebraska.
Ninth Circuit Finds that PURPA Gives FERC Broad Implementation Discretion, But Remands New Qualifying Facility Rules for Lack of NEPA Review
On September 5, 2023, the U.S. Court of Appeals for the Ninth Circuit (“Ninth Circuit”), in Solar Energy Industries Association v. FERC, held that the Public Utility Regulatory Policy Act (“PURPA”) gives FERC broad discretion to evaluate which implementation rules are needed to encourage the development of qualifying small-scale renewable generating facilities. While the Ninth Circuit did not vacate FERC’s decision, it remanded the decision back to FERC for failing to conduct the proper National Environmental Policy Act (“NEPA”) review. The decision stems from the Solar Energy Industries Association and several environmental organizations’ (collectively, “Petitioners”) challenge to Order Nos. 872 and 872‑A (collectively, “Order 872”), which were rules adopted by FERC that altered which small-scale renewable facilities qualify for benefits under PURPA and how those facilities are compensated (see July 20, 2020 edition of the WER).
Department of Energy Proposes New Program to Streamline Federal Authorizations to Site Interstate Transmission Projects
On August 10, 2023 in response to incentives made available through the Bipartisan Infrastructure Law and the Inflation Reduction Act, the U.S. Department of Energy (“DOE”) proposed reforms to its regulations governing the coordination of Federal authorizations for the development of interstate, onshore electric transmission facilities and to establish the Coordinated Interagency Transmission Authorizations and Permits Program (“CITAP Program”). The main goal of the CITAP Program, which will be administered by DOE’s Grid Deployment Office, is to “reduce the time required for transmission project developers to receive decisions on Federal authorizations for transmission projects.” Public comments are due by 11:59pm ET on October 2, 2023.
Mountain Valley Pipeline To Resume Construction After Supreme Court Vacates Fourth Circuit’s Order Halting Construction
On July 27, 2023, the U.S. Supreme Court vacated the U.S. Court of Appeals for the Fourth Circuit’s decision to grant the Wilderness Society’s motions to stay of construction on the Mountain Valley Pipeline (“MVP”) pending that court’s review of the Forest Service’s amended Forest Management Plan. The Supreme Court’s order grants MVP’s emergency application to vacate the Fourth Circuit’s stay orders and permits MVP to resume construction on the pipeline.
FERC Affirms Finding of Affiliation Over Appointment of Director
On July 3, 2023, FERC affirmed its earlier determination that Bluescape Energy Partners, LLC’s (“Bluescape”) appointment of a non-independent director to Evergy Inc.’s (“Evergy”) Board of Directors overcomes the rebuttable presumption of a lack of control under FERC’s regulations that normally applies when a company owns less than 10 percent of another company’s equity (see October 27, 2022 edition of the WER). Additionally, FERC clarified that the appointment of a non-independent director is a per se finding of control and found affiliation between Bluescape and Evergy, and therefore between Bluescape and Evergy’s public utility subsidiaries, pursuant to the definition of “affiliate” under FERC’s rules.
D.C. Circuit Backs FERC in New York Cost Allocation Dispute, Giving FERC Broad Deference under the Rule of Reason
On July 7, 2023, the U.S. Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) issued an opinion rejecting petitioner Hecate Energy Green County 3 LLC’s (“Hecate”) claim that the New York Independent System Operator (“NYISO”) tariff did not contain sufficient detail to put it on notice that NYISO would assess network upgrade costs resulting from non-jurisdictional projects. Instead, the Court agreed with FERC that because its tariff gave “fair notice,” NYISO “had not impermissibly adopted a practice that was not in its tariff.”
FERC Reverses Course, Rejects SPP Byway Cost Allocation Proposal for Second Time
On July 13, 2023, FERC on rehearing set aside its prior order that had accepted Southwest Power Pool, Inc.’s (“SPP”) proposal to establish a case-by-case process to allocate, on a regional, postage-stamp basis, all of the costs of a transmission facility with a voltage level between 100 kV and 300 kV (“Byway facility”). In setting aside its prior approval, FERC found that SPP’s Proposal granted the SPP Board too much discretion in allocating the costs of Byway facilities. Commissioners Mark Christie and James Danly each concurred with separate statements. FERC’s rejection marked the second time SPP’s proposal failed to obtain Commission approval.
FERC Adopts Regulations to Permit Credit-Related Information Sharing
On June 15, 2023, FERC issued Order No. 895, adopting new regulations permitting regional transmission organizations (“RTO”) and independent system operators (“ISO”) to share, amongst each other, credit-related information of their market participants, and requiring RTOs/ISOs to adopt tariff or similar rules for providing credit-related information sharing in order to better assess market participants’ credit risks.
House Subcommittee Holds FERC Oversight Hearing on Improving Reliability Through Energy Expansion, Interregional Transmission, and Backing Renewables with Fossil Fuels
On June 13, 2023, the House of Representatives Subcommittee on Energy, Climate, and Grid Security held a hearing on the “Oversight of FERC: Adhering to a Mission of Affordable and Reliable Energy for America.” The hearing focused on reliability and the transition from fossil fuel generation to renewable resources.
FERC Directs NERC to Develop New Transmission Planning Reliability Standard; Directs Transmission Providers to Submit One-Time Informational Reports on Extreme Weather Risk Assessment
On June 15, 2023, FERC issued two final rules aimed at boosting bulk power system resilience by improving how grid operators assess and plan for extreme weather impacts to the transmission system. One rule directs NERC to develop a reliability standard that requires transmission system planners to account for a range of extreme weather conditions, and the other rule directs each FERC-jurisdictional transmission provider to submit an informational report to the Commission that outlines its policies and processes for conducting extreme weather vulnerability assessments.