On May 3, 2023, a divided FERC voted 3-1 to deny a widely-supported complaint by multiple utilities in the Southwest Power Pool (“SPP”) region arguing that the absence of the new 15% generation Planning Reserve Margin (“Reserve Margin”) from the SPP tariff rendered that tariff unjust and unreasonable.  The Reserve Margin dictates exactly how much electric generating capacity load-serving utilities must own or have under contract to serve customers.  The complaining utilities argued that customers in SPP could be harmed by the costs associated with the rapid increase in the Reserve Margin with little corresponding reliability benefit and asked FERC to keep closer tabs on the process.  The utilities’ request for additional FERC oversight was opposed only by SPP itself.  As a result of the decision, SPP is free to change the Reserve Margin without any oversight by FERC or approval by a single state commission.   FERC further held that a complaint alleging that a key rate is missing from a tariff in violation of section 205 of the Federal Power Act and the Commission’s Rule of Reason fails to state a claim upon which relief could be granted. Continue Reading Divided FERC Announces Hands-Off Approach to Capacity Issues in SPP, Raises Questions About Tariff Detail Complaints

On February 21, 2023, FERC accepted PJM Interconnection, L.L.C.’s (“PJM”) proposed tariff revisions governing the Locational Deliverability Area Reliability Requirement (“LDA Reliability Requirement”) calculation, effective December 24, 2022, and applicable to the 2024/2025 Base Residual Auction (“BRA”), which was in progress at the time that PJM submitted its filing. Specifically, FERC accepted tariff changes that would allow PJM, during the BRA process, to exclude Planned Generation Capacity Resources from the LDA Reliability Requirement calculation if the addition of such resources materially increases the reliability requirement and such resources do not participate in the capacity auction. The February 21 Order also dismissed as moot a complaint filed by PJM challenging the justness and reasonableness of the existing LDA Reliability Requirement. Finally, the February 21 Order stated that FERC would soon convene a forum to examine the functioning of the PJM capacity market. Commissioner Danly issued a separate dissenting statement.Continue Reading FERC Accepts PJM Capacity Market Revisions to Locational Deliverability Area Reliability Requirement, Sparks Strong Dissent from Commissioner Danly

On January 27, 2023, FERC approved the Midcontinent Independent System Operator, Inc. (“MISO”) Transmission Owners’ (“TOs”) proposal to terminate reactive power charges and compensation under MISO’s Open Access Transmission, Energy, and Operating Reserve Markets Tariff (“Tariff”), effective December 1, 2022.  As a result, MISO will no longer charge transmission customers for reactive power service within the standard power range, and no generators, whether affiliated with the MISO TOs or not, will receive compensation for providing reactive power service within the standard power factor range.  Nevertheless, FERC’s determination does not affect MISO generators’ ongoing obligation to provide reactive power.  If MISO directs a generator to provide reactive power outside of the standard power factor range, the generator will be compensated based on existing mechanisms already included in MISO’s Tariff.  Continue Reading FERC Allows MISO Transmission Owners to Retroactively Terminate Reactive Power Compensation Back to December 2022

On January 19, 2023, the Commission issued a final rule that directs the North American Electric Reliability Corporation (“NERC”) to develop and submit reliability standards for monitoring high and medium impact bulk electric systems with high-speed internet connections. The Commission stated that the new reliability standards would assist entities in monitoring network traffic inside the bulk electric systems and detecting unauthorized activity inside those systems.Continue Reading FERC Directs NERC to Develop Internal Network Security Monitoring for High and Medium Impact Bulk Electric System Cyber Systems

On October 20, 2022, the Federal Energy Regulatory Commission (“FERC”) issued an Order rejecting a request by the California Public Utilities Commission (“CPUC”) seeking a rehearing of a Justification Order.  FERC’s Order declining rehearing comes after an October 7, 2020 filing where Tri-State Generation and Transmission Association, Inc. (“Tri-State”) filed its justification for spot market sales that exceeded the Western Electricity Coordinating Council (“WECC”) soft price cap of $1,000/MWh during the summer months of 2020.  On May 20, 2022, the Commission issued an order finding that Tri-State had sufficient justification for certain spot market sales above the soft price cap but had not justified amounts charged above the relevant index price.  Ultimately, the Commission rejected the CPUC’s rehearing request.Continue Reading FERC Affirms Use of Certain Price Indices for Justifying Prices above WECC Soft Price Cap

On February 22, 2022, FERC issued a Supplemental Notice regarding its planned Technical Conference on its Notice of Inquiry on Financial Assurance Measures for licenses, scheduled to take place on Tuesday, April 26 at 11:30am.

The Supplemental Notice provides a schedule for the program and proposed panel topics.  The first panel, Protecting Hydroelectric Facilities and

On December 16, 2021, the Federal Energy Regulatory Commission (Commission or FERC) issued a final rule amending its regulations governing the dam safety of FERC-licensed hydroelectric projects under the Federal Power Act (FPA).  FERC’s final rule follows its July 16, 2020 Notice of Proposed Rulemaking (NOPR) (see July 21, 2020 edition of the WER), which FERC issued following the 2017 spillway incident at the Oroville Dam and the May 2020 dam failures at the Edenville Dam and Sanford Dam in central Michigan.

The Commission explained that its final rule accomplished four objectives that are essential to improving its dam safety program under part 12 of its regulations.  First, it implements the two-tiered inspection program set forth in the NOPR, which will include a comprehensive assessment and a periodic inspection, each of which will be performed at a 10-year interval.  The comprehensive assessment will be more in-depth than the current part 12 inspections, will formally incorporate the existing Potential Failure Mode Analysis process, and will also require a semi-quantitative risk analysis.  The periodic inspection will be narrower in scope and primarily focused on performance of project works between comprehensive assessments.  This two-tier structure retains FERC’s current five-year interval between part 12 inspections at each Commission-licensed project and is consistent with the Federal Emergency Management Agency’s (FEMA) recommendation that “formal” inspections be conducted every five years.  FERC’s rule explained that this two-tier inspection scheme is similar to those used by the Bureau of Reclamation and the Army Corps of Engineers.
Continue Reading FERC Finalizes Revisions to Dam Safety Regulations

Summary of NOPR

On September 19, 2019, the Federal Energy Regulatory Commission (FERC) issued a Notice of Proposed Rulemaking (NOPR) proposing to revise its regulations implementing Sections 201 and 210 of the Public Utility Regulatory Policies Act of 1978 (PURPA) in light of changes in the energy industry since 1978.[1]
Continue Reading Executive Summary of FERC’s Notice of Proposed Rulemaking regarding the Public Utility Regulatory Policies Act of 1978

On August 9, 2019, the Federal Energy Regulatory Commission (“FERC”) ruled that hundreds of millions of dollars of ongoing and future investments by Chelan County Public Utility District (“Chelan PUD”) in the Rock Island Hydroelectric Project qualified as early-action investments under the new section 36(c) of the Federal Power Act (“FPA”).  Accordingly, FERC will consider these significant investments when the Rock Island Project undergoes relicensing of its FERC license prior to the 2028 expiration of the license.
Continue Reading FERC Approves First-Ever Determination on Early-Action Investment Credit Under Section 36 of the Federal Power Act